Regarding newly issued revised DCD drawing for LPG tank at 1st floor

Regarding newly issued revised DCD drawing for LPG tank at 1st floor

Date: xxx

Ref. xxx

To:                     M/s. xxx , Metal Wowks

Project:              2B + G + 14 + Lower Roof Hotels Building on Plot No. xxx at Barsha, Dubai

Subject            : Regarding newly issued revised DCD drawing for LPG tank at 1st floor

Dear Sir,

With reference to above, we would like to intimate you that we have received revised DCD drawing for LPG tank at 1st floor. Please review the drawing and intimate us the impact of your scope of work

This is for your kind information to take immediate action.

Regards,
For xxx Contracting L.L.C

xxx

Project Manager