Date: xxx
Ref: xxx
Kind Attn :Mr. xxx
Project: 2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai
Subject: Reply – Notification of Delay
Dear Sir,
This is further to your letter ref. AAEC/DB/3244/22/AS dated 15th February 2022, most of the items has submitted and under engineering approval process. The balance three items will be submitted within next week. Following are the MMC response.
SL | ATRIUM COMMENTS | MCM RESPONSE |
1 | Submission of MDB, DB and SMDB: Negative 6 days. | Supplier and manufacture prequalification under review, will be submitted by 25th February 2022. |
2 | Submission of water transfer pump sets: Negative 75 days | First revision was submitted on 20-Jan-22 and resubmitted on 10- Feb 22 as per consultant comments. |
3 | Submission of sump pump: Negative 73 days | First revision was submitted on 20-Jan-22 and resubmitted on 12-Feb-22. |
4 | Submission of booster pump: Negative 69 days | First revision was submitted on 20-Jan-22 and resubmitted on 12-Feb-22. |
5 | Submission of circulation pump: Negative 69 days | First revision was submitted on 20-Jan-22 and resubmitted on 12-Feb-22. |
6 | Submission of GRP panel water tank: Negative 49 days | Submission is under review, will be submitted by 22-Feb-22. |
7 | Submission of FCU: Negative 49 days | Submitted on 17-Feb-22. |
8 | Submission of variable refrigerant unit: Negative 56 days | Submitted on 17-Feb-22 |
9 | Submission of exhaust fan: Negative 49 days | Under review, will be submitted by 25-Feb-22. |
We would like to highlight that, despite of multiple obstruction from authority, neighbor for the swimming dewatering work, we have recovered the delay and now it’s almost 0 float for construction activity. The delay in engineering submission and approval will also be recovered soon.
Regards,
For xxx Contracting L.L.C.
xxx
Project Manager