Construction Labor

Manpower Requirement

Date: 20.02.2017 Kind Attn:       Mr. xxx| Mr. xxx| Mr. xxx Project:         2B + G + 14 + Lower Roof Hotel Building Plot No.:        373-1297 at Barsha, Dubai Subject:       Manpower Requirement Dear Sir, Good Day! Pertaining to the subject, we have the following concerns regarding Manpower allocation at Site: From 01 Feb,2017 to 09 Feb, […]

Manpower Requirement Read Post »

Engineer's Training

Replacement of Mrs. xxx during her leave period

Date: 28.09.16 Ref:  CC/HR/003 Kind Attn:         HR Department Project:            2B + G + 14 + Lower Roof Hotel Building Plot No.:           373-1297 at Barsha, Dubai Subject:          Regarding replacement of  Mrs.Preethi Suhail during her leave period Dear HR, With ref. to above, kindly replace Mrs. xxx with Miss. xxx for the position if Site Technical

Replacement of Mrs. xxx during her leave period Read Post »

Construction Labor

Issue of non-availability of Labour

Date: xxx CC/HR/003 Kind Attn:       HR Department Project:         2B + G + 14 + Lower Roof Hotel Building Plot No.:        373-1297 at Barsha, Dubai Subject:       Issue of non-availability of Labour Dear HR, With ref. to above, the Labour who has worked at Citymax site yesterday dt.13.07.16 till 11 PM are supposed to be coming

Issue of non-availability of Labour Read Post »

Statement

Issue of Mr.xxx and his settlement

Date: xxx CC/HR/002 Kind Attn:         HR and Accounts department Project:             2B + G + 14 + Lower Roof Hotel Building Plot No.:            373-1297 at Barsha, Dubai Subject:           Issue of Mr.Dilip Saigal and his settlement Dear Mr.Vinod Arora and Mr.Vasu Dev Mehtan, With ref. to above Mr.xxx who was PM at site during casting of

Issue of Mr.xxx and his settlement Read Post »

Broken Tiles

Our observation on the tiles delivered at the site and awaited for your response

Date: 12.10.16 Ref:   CC/269/EVT/01 To:                   The Manager, xxx General Trading LLC Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. 373-1297 at Al Barsha 1st, Dubai, and U.A.E Subject:           Our observation on the tiles delivered at the site and awaited for your response Dear Sir, With ref. to above, as per

Our observation on the tiles delivered at the site and awaited for your response Read Post »

Chiller

Regarding requirement of Contract Agreement for Chillers

Date: xxx           Ref:     CC/269/JC/01 To:                   M/s. Johnson Controls Kind Attn:       Mr. xxx Azad Project:           2B + G + 14+ Lower Roof Hotel Building on Plot No. 373-1297 at Al Barsha 1st, Dubai, U.A.E Subject:     Regarding requirement of Contract Agreement for Chillers Dear Sir, With ref. to above, as you are the nominated contractor by

Regarding requirement of Contract Agreement for Chillers Read Post »

cutting the toilet wall tile

Client instruction to contact you for quotation to resize/ cutting the toilet wall tile due to size issue in the supply.

Date: xxx CC/HARJ /001/17 To:                   M/s. xxx Bldg. Mat & Marbles TR. Project:               2B + G + 14+ Lower Roof Hotels Building on Plot No. 373-1297 at Barsha, Dubai Subject:           Regarding client instruction to contact you for quotation to resize/ cutting the toilet wall tile due to size issue in the supply. Dear

Client instruction to contact you for quotation to resize/ cutting the toilet wall tile due to size issue in the supply. Read Post »