METHOD STATEMENT FOR INSTALLATION AND TESTING OF FIRE SPRINKLER SYSTEM

Method Statement Title: Installation of Sprinkler Piping System

Method Statement Title: Installation of Sprinkler Piping System

Method Statement Title: Installation of Sprinkler Piping System

Scope

The scope of this method statement is to describe the method of installation of sprinkler piping system in Burj Dubai – The Residences Project in accordance with the project specifications.

            Note

a.         Installation of stand pipes and fire hose reels is covered under a separate method statement Ref. ETA/MS/P-05

b.         For testing and commissioning of sprinkler system refer to method statement Ref: ETA/MS/P-14.

2.0       Material

            2.1       Sprinkler pipes to ASTM A536 GR `B’

            2.2       Zone Control Valve 

            2.3       Test and Drain Valves

            2.4       Alarm valves

            2.5       Pressure gauges

            2.6       Flow switches

            2.7       Pressure reducing valves

            2.8       Water motor gong

            2.9       Other associated materials

3.0       Applicable Location

            Towers, East and West Podiums and Villas. 

4.0       Method

4.1       Storage  

4.1.1    All material while unloading shall be lowered to the ground either manually or with mechanical aid like crane depending on the quantity of the pipe and should not be dropped to the ground.

4.1.2    For pipes, timber supports shall be placed beneath at equal distance.   

4.1.3    Pipes shall be stacked on a flat surface with adequate supports.

4.1.4    End caps of pipes shall be in place until removed for installation.  

4.1.5    While stacking, it shall be ensured that pipes of bigger sizes are placed below and smaller sizes on top.   

                        4.1.6    All pipes shall be covered and shall not be exposed to direct sunlight.  

                        4.1.7    All other items such as valves, gauges, switches shall be kept on racks within site stores and shall be segregated as per size, model, type etc. for easy retrieval.

                        4.1.8    Any items found damaged or not suitable as per project requirements shall be removed from site.  If required to store temporarily, they shall be clearly marked and stored separately to prevent any inadvertent use. 

            4.2       Preparation

  • Check and ensure all drawings used for installation are latest and approved for construction.
  • Check the coordination of piping layout with other services and reflected ceiling and resolve problems, if any.
  • Mark the pipe routing on the ceiling as per approved drawings.   

            4.3       Installation

                        4.3.1    Fix supports and hangers with approved material, as per approved layout drawings. 

                        4.3.2    Cut all excess hanger rods to leave only 25mm lengths below the support for final adjustment of levels, if required.

                        4.3.3    Machine cut the pipes square to required length and ream the pipes to remove burrs and clean thoroughly before installation. 

                        4.3.4    Pipe work upto 50mm shall have threaded joints and pipes 765mm and above shall be with grooved coupling joints.   The pipe work shall be grooved and installed as per coupling manufacturers instruction and grooving equipment as supplied by manufacturer shall be used. 

                        4.3.5    Install pipe work at heights and to gradients shown on approved drawings, in a neat and tidy manner.         

                        4.3.6    Holesaw cutter shall be used to cut holes in the pipe work where required for fixing mechanical Tees etc.

                        4.3.7    PVC Sleeves of suitable sizes shall be provided at wall crossings and fire stopping with approved material shall be completed. 

                        4.3.8    Only standard fittings shall be used for changes in directions, reduction in pipe sizes, Tee joints, etc.   Only long radius bends shall be used where required.

                        4.3.9    Expansion couplers shall be installed at location where piping crosses the building expansion joints (Refer Annexure-I for manufacturer’s recommendations).

                        4.3.10  All vertical pipes shall be installed plumb with at least 25mm clearance from the wall / surface.

                        4.3.11  Install valves, supervisory switches, flow switches, pressure gauges etc. as per approved drawings and manufacturer’s instruction.

                        4.3.12  Install drain valves at all low points as shown on approved drawings and ensure that water can be drained from all sections of pipe work.

                        4.3.14  Inspectors test drain valves of suitable size shall be provided at the farthest point in the system in each zone as per approved drawings. 

                        4.3.15  Check and ensure easy access is available for maintenance and removal of all components such as valves, switches etc.

                        4.3.16  The droppers for sprinkler heads are installed at location as per approved layout / coordinated drawings (Refer Annexure-II). 

                        4.3.17  Plug or cap-off all open ends in the piping during the installation phase. 

                        4.3.18  Flush and clean the entire piping with clean water until the system is clean. 

                        4.3.19  Install correct type of sprinkler heads as per approved drawings and manufacturers instruction. 

                        4.3.20  Clean the pipe work thoroughly to remove all dirt, soil,  oil, etc. and apply one coat of primer.

                        4.3.21 Provide identification and flow directional arrows to the pipe work, valves and other components as per approved submittals / details.

                        4.3.22  The entire installation shall be supervised, checked and certified by FIREX prior to testing and commissioning of the system.

                        4.3.23  The details of the entire installation of the system shall be inspected and approved by the Dubai Civil Defence Authority.

5.0       Testing & Commissioning

5.1       The entire pipe work shall be hydrostatically pressure tested as per method statement Ref. ETA/MS/P-011 (Refer Annexure-III).

5.2       The final testing and commissioning of the system shall be carried out as per Method Statement Ref.ETA/MS/P-014 (Refer Annexure-IV).

  • Water Supply Treatment
  • NFPA 13-9-1.5 states “In areas with water supplies known to have contributed to micro biologically influenced corrosion (MIC), water supplies shall be tested and appropriately treated prior to filling or testing of metallic piping systems” .
  • But, the chemical composition of DEWA water clearly shows that there is no  microbiologically influenced corrosion. As water from DEWA is filled in the fire protection system, water treatment is not required for the wet system (Annexure-V).  

7.0       Safety

            7.1       Warning signs shall be placed at required location during pressure testing of the pipe work and barriers where required to protect other services. 

            7.2       All precautions shall be followed as per established project safety procedures. 

8.0       Records

8.1       Work Inspection Request (WIR) duly signed by Consultants and NMX.

            8.2       Installation check lists signed by ETA QA/QC  &  NMX.

            8.3       Installation report / certification by specialist fire protection contractor.

9.0       Attachments

            9.1       Test Certificate for Piping System

EngineersBlog Home | Method Statement Title: Installation of Sprinkler Piping System – Method Statement Title: Installation of Sprinkler Piping System

{ “@context”: “https://schema.org”, “@type”: “Article”, “headline”: “Method Statement Title: Installation of Sprinkler Piping System – Method Statement Title: Installation of Sprinkler Piping System”, “description”: “All material while unloading shall be lowered to the ground either manually or with mechanical aid like crane depending on the quantity of the”, “author”: { “@type”: “Person”, “name”: “Md Abu Zaed Khan” }, “datePublished”: “2022-11-06T21:53:49+04:00”, “dateModified”: “2022-11-06T21:54:07+04:00”, “url”: “https://engineersblog.net/method-statement-title-installation-of-sprinkler-piping-system/” } { “@context”: “https://schema.org”, “@type”: “BreadcrumbList”, “itemListElement”: [ { “@type”: “ListItem”, “position”: 1, “name”: “Home”, “item”: “https://engineersblog.net/” }, { “@type”: “ListItem”, “position”: 2, “name”: “Method of Statement”, “item”: “https://engineersblog.net/method-of-statement/” }, { “@type”: “ListItem”, “position”: 3, “name”: “Method Statement Title: Installation of Sprinkler Piping System – Method Statement Title: Installation of Sprinkler Piping System”, “item”: “https://engineersblog.net/method-statement-title-installation-of-sprinkler-piping-system/” } ] }

Leave a Comment

Your email address will not be published. Required fields are marked *

Scroll to Top