Method Statement Title: Chlorination, Disinfection and

Method Statement Title: Chlorination, Disinfection and Commissioning of Domestic Water System

Related posts:
Method Statement Title: Installation & Testing of Above Ground Drainage Piping
Method Statement for (ppr) Water Supply System

1.0     Scope :

            To describe the method of flushing, Disinfecting and chlorination of domestic water

System as per specification Section 15400 Clause 3.07.

2.0     Material :

  • Copper pipes.
    • PR PVC pipes.
    • Pex pipes.
    • Valves fixed in the system
    • U/G and overhead water tanks.
    • Other associated materials.

3.0     Applicable locations and Description :

  • E1, E2, E3, W1, W2 & W3 Towers, East & West Podiums and Villas.
    • Water supply line (Main)
    • Water distribution line (Branches).
    • Water service lines (Supply to fixtures)

4.0     Method :  Refer enclosed details.

  • Safety
  • Warning sign boards shall be displayed near all faucets outlets which are accessible to public during chlorination and pressure testing.
  • Workers shall use protective hand gloves, masks and PPE as required.
  • Sodium Hypochlorite (Liquid chlorine) shall be stored in shaded area.
  • Care must be taken while opening the container lid.