METHOD OF STATEMENT FOR DRAINAGE PIPE INSTALLATION INSIDE THE TOILET

Method Statement Title: Acoustic Insulation to Drainage

Method Statement Title: Acoustic Insulation to Drainage Pipes

Method Statement Title: Acoustic Insulation to Drainage Pipes

Scope

  1. This method statement applies to installation of acoustic insulation for drainage piping.
  • Purpose
  • Purpose of this method statement is to outline the method of storage, handling and installation of acoustic lining for drainage piping.
  • Materials
  • Revac SGQ 50-25FF Metallic foil faced flexible polymer sheet laminated to quilted glass wool approximately 24mm thick, tested to ISO 140-3/95.
  • Method
  • Receiving
  • When received at site, each pallet shall be checked for quantities, model numbers, physical damages, etc.
  • Receiving inspection shall be checked by Storekeeper, Engineer and QC Engineer, which shall be documented.
  • Storage
  • All Revac pallets are stored in a covered store.
  • Storekeeper will be responsible for proper storage and maintenance of records, as required.
  • Installation
  • The following areas of drainage pipes will be covered by acoustic lining.
  • High-level drain pipes in living areas/bed rooms, entrance foyers of apartments, lift lobbies, main lobby/reception areas, control room/offices, kitchens, bathrooms and any other occupied space.
  • Clean the drainage pipes prior to commencement of acoustic lining.
  • Wrap the pipes and fittings by Revac SGQ 50-25 FF sheets.
  • Revac SGQ 50-25 FF can cover either butt joint or overlap joint.
  • Aluminium foil tape should be used at maximum 250mm centers. All joints should also be covered with aluminium foil tape. Cut ends of glass fibre shall be enclosed by tape.
  • Vertical pipe lagging may require the acoustic barrier to be adhered to pipe to stop the material moving.

Note     Refer attached manufacturer’s instructions.

  • Inspection
  • Acoustic lining for drainage pipes shall be witnessed during false ceiling clearance inspections.
  • Safety
  • All safety precautions shall be followed as per established project safety plan and procedure.
  • Only experienced and skilled insulators shall be engaged for carrying out this work.
  • The people involved in the insulation shall have PPE safety helmets, safety shoes, gloves, etc., as required.
  • Safety officer shall check and ensure that all safety precautions are followed.
  • Safety officer shall check and ensure that all scaffolding and ladders used at site are having duly signed tags.
  • References
  • Manufacturer’s catalogue.
  • Approved submittal for acoustic lining for drainage piping. Ref. Submittal P-003.
  • Shop drawings.
  • Records
  • Work Inspection Request (WIR) duly signed by the Consultant.
  • Attachments

9.1       Manufacturer’s instructions.

EngineersBlog Home | Method Statement Title: Acoustic Insulation to Drainage Pipes – Method Statement Title: Acoustic Insulation to Drainage Pipes

{ “@context”: “https://schema.org”, “@type”: “Article”, “headline”: “Method Statement Title: Acoustic Insulation to Drainage Pipes – Method Statement Title: Acoustic Insulation to Drainage Pipes”, “description”: “Purpose of this method statement is to outline the method of storage, handling and installation of acoustic lining for drainage piping”, “author”: { “@type”: “Person”, “name”: “Md Abu Zaed Khan” }, “datePublished”: “2022-11-06T21:35:40+04:00”, “dateModified”: “2022-11-06T21:36:40+04:00”, “url”: “https://engineersblog.net/method-statement-title-acoustic-insulation-to-drainage-pipes/” } { “@context”: “https://schema.org”, “@type”: “BreadcrumbList”, “itemListElement”: [ { “@type”: “ListItem”, “position”: 1, “name”: “Home”, “item”: “https://engineersblog.net/” }, { “@type”: “ListItem”, “position”: 2, “name”: “Method of Statement”, “item”: “https://engineersblog.net/method-of-statement/” }, { “@type”: “ListItem”, “position”: 3, “name”: “Method Statement Title: Acoustic Insulation to Drainage Pipes – Method Statement Title: Acoustic Insulation to Drainage Pipes”, “item”: “https://engineersblog.net/method-statement-title-acoustic-insulation-to-drainage-pipes/” } ] }

Leave a Comment

Your email address will not be published. Required fields are marked *

Scroll to Top