METHOD STATEMENT FOR WIRES AND CABLES INSTALLATION

Method Statement for Installation of Emergency Lighting

Method Statement for Installation of Emergency Lighting System

Related posts:
Inspection Check List for Installation of Central Battery System
Quality Control Procedure for Ups & Accessories Installation

 Client       Consultant     Contractor     Issued on  
 Prepared ByReviewed byApproved byMS
Rev.NameDateNameDateNameDateNo.
        
   


TABLE OF CONTENTS

1. PurposePage 03
2. ScopePage 03
3. Legislation and Code of PracticePage 03
4. ReferencePage 03
5. Definitions   6. ResourcesPage 03   Page 04
6.1. EquipmentPage 04
6.2. Safety of Equipment’sPage 04
  7. Safety Precautions  Page 04
7.1. Construction HazardsPage 04
7.2. Personal Protective EquipmentPage 05
7.3. Safety Training and Emergency proceduresPage 05
7.4. First AidPage 05
  8.Detailed Construction Sequence (Methodology)  Page 06
8.1. ProcedurePage 06
  9.Construction Program 9.1 Housekeeping   9.2 Protection of Executed Works   9.3  Responsibilities   9.4 Records   10.Inspection and Testing 11.Related Forms 12.Attachments  Page 09 Page 09 Page 09 Page 09 Page 10   Page 10 Page 10 Page 10
  
  
  
  
  
  
  
  
  
  


1. Purpose

This document describes the methodology for the installation of emergency Lighting central battery System in Project, and to ensure that all concerned persons are familiar with the sequence of activities, utilization of resources, and execution of the works in compliance with applicable Safety and Quality Procedures, and Project Documents and Specification.

2. Scope of Works

This document covers the following scope of works:

This method statement is intended to outline the activities and the methods used for installation of Emergency Lighting System. All activities will be carried out in accordance with the contract details and in full compliance to the Contract Specifications and Documents. All work within the rights-of-way of the local municipal governments will be done in compliance with requirements issued by those agencies.

3. Legislation and Code of Practice

  • IEE Wiring Regulations.
  • NFPA 72.
  • All related codes and standards referenced in the Contract Specifications

4. Reference

  • Electrical Specification General Requirements.
  • Electrical Specification Emergency Lighting System
  • Contract Related Drawings, Codes & Standards. 

5. Definitions

Client                    :             

Consultants         :             

PMC                      :             

Contractor           :             

6. Resources

6.1. Equipment / Tools

  • Crane, Trolley, Chain Block, Rollers, etc
  • Hand Tools
  • Flat Files
  • Measuring Instruments
  • Ladders/Scaffolding
  • Drilling Machine
  • Standard Electrical Tool Box
  • Hand Gloves, Fall Protection Equipments (and other PPE as necessary)

6.2 Safety of Equipment’s

Necessary measures will be taken for the safety of the equipment and any other works affected by the works subject of this document. Relevant entities which might require protection include any such works in the vicinity of the area of work or on the service access or discharge path. The construction team will ensure that any such requirements are documented.

7. Health, Safety & the Environment

  •  A task based risk assessment and mitigation strategy is summarized in the attached table. Work will commence as per safety regulations laid down in the contract specification and project safety plan.
  • Safety gears shall be used. All personal protective equipment shall be used as appropriate according to the nature of the job. For electrical works, provide nonconductive tools and PPE.
  • Working on live power cables/equipment is not allowed. ELCB shall be used in temporary panel boards; industrial connectors/sockets for temporary power cable connections.
  • Always maintain cleanliness in work areas. Housekeeping shall be of good standard and all cut pieces and debris shall be removed by the end of workday. Ensure that all lifting operations are carried out as per approved procedures and safety regulations.
  • Ensure that adequate barricade and signage “DANGER KEEP-OUT, HEAVY LIFTING IN PROGRESS” is provided around the affected area. Work will be executed through Permit to Work system.
  • All scaffoldings shall be checked by competent person and should carry green tags “safe to use”, prior to use for working purpose.
  • All plant tools tackles will have valid certificate. Lifting machines, appliances and gear to be examined by qualified rigger and come with valid certification.
  • Workers working at height to wear their full body harness and should be anchored to a rigid point. Nobody is allowed to stand on the top of the step ladder; worker should stand two rungs below from top of the step ladder. A co-worker must hold the step ladder while in use. Work inside shafts are not allowed without work permit and supervision. Work areas to be provided with proper lighting and ventilation at all times.
  • Store tools and equipment and unused materials stacked in a safe area at the end of the workday.
  • Method statement / risk assessments to be briefed to all concerned personnel and signed as read /understood.

7.1 Construction Hazards (tick as appropriate)

CorrosiveOxidizingHighly flammableExtremely flammableToxicHighly ToxicIrritatingHarmful
þooooooo
ExplosiveDanger for the EnvironmentConstrained SpaceSlippery SurfaceDanger of ElectrocutionFalling from HeightOther
o____________________
o____________________
o____________________
oooþþþo____________________

The hazards identified above will be controlled under the overall Project Safety Plan which is a separate document communicated to all parties on the project.

7.2. Personal Protective Equipment (tick as appropriate)

The works subject of this document requires that the following PPE be used:

Safety PrecautionHelmetHi-VizEye ProtectionFace ProtectionMask RequiredRespirator RequiredEar Protection
 þ þþþ  
Gloves RequiredSafety Shoes RequiredProtective ClothingSafety HarnessEquipment GuardsLifejacketOther
o Hot Work Permit Required
o____________________
o____________________
þþþþo o____________________

7.3. Safety Training and Emergency procedures

Before commencing any works, all employees will attend a site safety induction training to ensure all safety measures are understood and implemented and to cover specific procedures in case of emergency. If necessary, practical training exercises will be conducted on escape routes, signage, evacuation and rescue.

7.4. First Aid

Prior to the commencement of work, arrangements will be made for medical facilities and medical personnel to be available from prompt attention to the injured person. The contractor’s vehicle assigned to the job site will be used for transporting the injured person to the first aid station and to the nearest hospital when required.

Name of On-Site First Aider/s: 
  
First Aid Box Location: 
  
Location of Nearest Hospital: 
  
First Aid and Medical Supplies available at site:
Potable WaterIce Cubes
10x6cm Sterile Gauze Pad4x6cm Gauze Roller Bandage
10x10cm Sterile Gauze Pad8x10cm Gauze Roller Bandage
Large Sterile Gauze Pad10x12cm Gauze Roller Bandage
Burn Dressings5cm Elastic Bandage
7.5cm Elastic Bandage10cm Elastic Bandage
Triangular BandageBarrier Device for CPR
Adhesive Skin TapeAdhesive Leucoplast Tape
Emergency BlanketSafety Pins
First Aid ScissorsTweezers
Disposable GlovesInstant Cold Pack
Non-prescription Medicines (Aspirin, Ibuprofen, Acetaminophen)First Aid and Burn Spray, Deep Heat Spray

8. DETAILED CONSTRUCTION SEQUENCE (METHODOLOGY)

Note: All documentary requirements for this purpose shall be submitted for approval and this shall include Manufacturers data, certificate of compliance, brand designation, type and class including samples.

8.1. Procedure

No.Description of ActivityResponsibility
PRE-INSTALLATION PROCEDURE
1.0All workers to attend safety induction conducted by main contractor and given specific Training on the safe installation methods.Install Security System as indicated on the approved shop drawing and as per specification and according to manufacturer’s recommendation.Install Security System as indicated on the approved shop drawing and as per specification and according to manufacturer’s recommendation.The Site Supervisor/Foremen will also check that proper tools and equipment are available to carry out the work and are in compliance with contract specification.Site Supervisor also explains to the tradesmen regarding safety the precautions to be observed.CM/PE
 INSPECTION AND GUIDANCE 
2.0Many of the installation requirements included in the procedures will come from the Supplier. Care should be taken to ensure that the requirements of the manufacturer and any of his technical manual (s) have been included. Ensure the specified test on plant and equipment will not invalidate the manufacturer’s/supplier’s warranty. The Supervisor will complete the inspection checklist and follow the Inspection & Test Plan detailed in this procedure. The intent of this procedure is to establish a high level of assurance that the end product meets the specification requirements.The QA/QC Inspectors should verify the approved procedures are followed and the inspections and testing records are completed. 
 TRAINING & QUALIFICATONS OF PERSONNEL 
3.0All operatives will attend safety induction along with the relevant document copies i.e. valid visa company ID copy, and copy of previous experience and training in the same job which proves his competency.Supervisor should closely monitor the activity, if he finds any operative is lagging on safe work competency, he will be sent for re-induction and even retraining if deemed necessary.Examine the areas to execute the work and the conditions under which the work will be performed. Identify conditions detrimental or unsafe for the proper and timely completion of the Work. Do not proceed until unsatisfactory or unsafe conditions have been corrected.Examine the areas to execute the work and the conditions under which the work will be performed. Identify conditions detrimental or unsafe for the proper and timely completion of the Work. Do not proceed until unsatisfactory or unsafe conditions have been corrected.CM/PE/SK
 INSPECTION & STORAGE OF MATERIALS 
4.0Submit Notification of Permanent Material Received on Site i.e. Material Inspection Request upon receipt of materials delivery to site. Attach Delivery Receipt, Material Submittal Approval and other documents to show complete compliance with specifications and QA/QC Plan.Any material found not as of approved material or with surface damage which is not rectifiable will be set aside. These materials will be labelled and returned to supplier warehouse and a Non-conformance Report will be issued to the supplier by QAlQC superior.Deliver and store materials in manufacturer’s original packaging labelled to show name, brand, type and grade.Store materials in protected dry location off-ground in accordance with manufacturer’s instructions. Survey and check site for material delivery accessibility. Lay down area at site to be coordinated with main contractor and arrangements to be made for unloading and / or mobilization of materials.Ensure all the hoisting chain / belts are in good condition and checked by specialist third party and valid certificate are to be provided prior to any lifting activity unloading of materials at designated storage area and ensure no blockage to any access.Ladders / Scaffoldings to be secured firmly over the working platform and inspected by competent personnel and tagging system (green/red) are implemented, prior to start of work.Prior to commencement of work, the Engineers & Supervisor/Foreman will inspect all materials delivered to work place are checked for with their shipment check list and ensure they are the relevant piece for the site and materials are not damaged, without excessive scratches or visible corrosion.Only required materials to be shifted to site and stored temporarily and ensure extra materials are not dumped to site and congest the working area. Once work is completed extra materials and tools to be return back to stores, work area to be kept clean.   
INSTALLATION PROCEDURE I SEQUENCE OF WORK
1.0Make sure that conduiting / raceways for CB system are already installed and approved.PE/SE/Applicator
2.0Surface Mounted Luminaries (Emergency & Exit lights): 2.1: Make sure the wall or ceiling is ready, clean and in acceptable condition prior to fixing the luminaries. 2.2: Install luminaries as per latest approved emergency lighting layout drawings and as per manufacturer recommendations, with all connections/wiring. Height & location to be as per approved drawings. 2.3: Make sure the type and size of the wire is correct as per specification, approved material submittal and civil defence requirements. 2.4: Ensure the raceways or conduits used for the emergency lighting are not used for other systems. 2.5: Make sure the wiring is done as per manufacturer wiring diagram unless otherwise indicated. 2.6: After the installation is complete cover the luminaries with polythene plastic as protection against dirt, moisture, paint and other construction debris.SE/Applicator
3.0Recessed Mounted Luminaries (Emergency & Exit Lights): 3.1: Make sure the wall or ceiling is ready, clean and in acceptable condition prior to fixing the luminaries. 3.2: Install luminaries as per latest approved reflected ceiling plan layout, emergency lighting layout drawings and as per manufacturer recommendations, with all connections/wiring. Height & location to be as per approved drawings. 3.3: Make sure the type and size of the wire is correct as per specification, approved material submittal and civil defence requirements. 3.4: Ensure the raceways or conduits used for the emergency lighting are not used for other systems. 3.5: Make sure the wiring is done as per manufacturer wiring diagram unless otherwise indicated. 3.6: After the installation is complete cover the luminaries with polythene plastic as protection against dirt, moisture, paint and other construction debris.SE/Applicator
4.0Central Battery Panel & Central Monitoring Unit: 4.1: Install central battery panel and central monitoring unit based upon the latest approved layout drawings and manufacturer recommendations. 4.2: Ensure the position and orientation of the panels is as per approved general arrangement shown on the approved detail drawings. 4.3: For central battery panels, make sure holes are provided on the base plate of the cabinet for floor anchoring or bolting to a fixed base. 4.4: Use appropriate size of bolts/anchors for fixing the central battery panels and make sure panels are levelled and plumbed. 4.5: Either cable tray or trunking should be available to contain all the home runs above the panels. 4.6: Wiring and connections shall be done as per panel manufacturer’s wiring diagram unless otherwise indicated. 4.7: Other components of the CBS shall be installed as per manufacturer catalogue and instructions provided with them and included in material submittals. 4.8: Containment for the CBS Cabinets shall be done as per the requirement of the emergency lighting system and approved containment shop drawings. 4.9: Panel board shall be located and installed with the maintenance distance for the accessible doors to open and close without any restrictions. 4.10: After the installation is complete cover the CBS panels with polythene plastic as protection against dirt, moisture, paint and other construction debris.SE/Applicator

9. Construction Programs.

  • As per main program

9.1 Housekeeping

The work area shall be maintained neat and tidy as reasonable practical at all times.

9.2 Protection of Executed Works

Executed works in areas where other works are still being carried out shall be protected as per the contract requirements.

9.3 Responsibilities

PositionOverall Resp.SupervisePerformShort Description
Project Manager oo 
Construction Manager oo 
Project Engineero o 
Site Engineeroü  
Land Surveyorooo 
Safety Engineeroüo 
QA/QC Engineero     üo 
MEP Coordinatorüüo 
General Foremano     üo 
Foremanooü 
Charge handooü 
Laboureroo     ü 
Helperoo     ü 

9.4 Records

In accordance with the Quality Management System, the following records will be maintained as documentary evidence of the establishment of this method statement:

Records to be retainedResponsibilityMinimum Retention PeriodDisposition
Work Notification ( If required)Construction ManagerAs per Contract Requirements 
Request for Inspection ( RIW )QA/QC EngineerAs per Contract Requirements 

10. INSPECTION & TEST PLAN

  1. The engineer should verify that the supervisor/foreman with construction responsibilities for installation is familiar with this method statement and is issued with copies of the inspection checklists and test plans.
  2. The engineer should satisfy the procedures provided by QA/QC inspections to ensure the as-installed condition of the Emergency Lighting System installation meets the specified engineering requirements and approved drawings.
  3. As part of the assessment, the QC Inspection Procedures must ensure a quantitative or qualitative acceptance criteria for determining the prescribed activities have been accomplished satisfactorily.
  4. The QC inspection personnel, in coordination with Site Supervisor, should verify that the quality of the related Emergency Lighting System installation activities is within the prescribed criteria.
  5. The Supervisor should verify any as-built record of Emergency Lighting System installation, and confirm that the information meets the project requirements.
  6. Quality Control Engineer along with Project Engineer and Site Supervisor will monitor that all components are installed as per contract specifications, manufacturer instructions and approved submittals.
  7. Request for Work Inspection Request (WIR) shall be submitted by Site Engineer to QA/QC Department for verification and inspections.
  8. Readable stamped approved drawing to be available during installation and inspection.
  9. QA/QC Department will forward WIR to QA/QC for inspection and approval in accordance with ITP.
  10. All the equipment’s engaged for testing shall have a valid calibration and certificate should be furnished.

11. Related Forms

  • As per standard checklists for inspection of installation and testing checklist provided by supplier.

12. Attachments

  • Inspection & Testing Plan EL/ITP-00
  • Check list for installation : EL/ICL – 00
  • Risk Assessment : EL/RA – 0

Related Articles

Leave a Comment

Your email address will not be published. Required fields are marked *

Scroll to Top