METHOD STATEMENT FOR ELECTRICAL GALVANIZED CONDUITS INSTALLATION – METHOD STATEMENT FOR Electrical Galvanized Conduits installation
METHOD STATEMENT FOR ELECTRICAL GALVANIZED CONDUITS INSTALLATION
- TABLE OF CONTENTS
1. SCOPE
2. definitions
3. HEALTH AND SAFETY
4. OPERATION
5. installation and fixation
6. RESPONSIBILITIES
7. MANPOWER REQUIRED
8. MATERIALS REQUIREMENTS
9. EQUIPMENTs REQUIREMENTs
10. WASTE MANAGEMENT
11. SPECIAL CONTROL MEASURES.
12. SUPPORTING DOCUMENTATION
13. DISTRIBUTION
1.SCOPE
- This procedure to clear the method of the supply, installations of Electrical Galvanized Conduits for the project.
- This document details Electrical Galvanized Conduits Installation:
- Preparation of work.
- Delivery and inspection upon arrival of material at site.
- Installation of the system.
2. definitions
PQP : Project Quality Plan
PSP : Project Safety Plan
QCP : Quality Control Procedure
HSE : Health, Safety and Environment
MS : Method Statement
ITP : Inspection Test Plan
QA/QC : Quality Assurance / Quality Control Engineer.
WIR : Inspection and Test Request
MIR : Material Verification Record.
3. HEALTH AND SAFETY
- Strictly followed as per the manufacturer’s Health and Safety recommendations for handling and use of the materials.
- Ensure all involved personnel shall be aware of the same.
- Specific safety measures have to follow as applicable, and all the safety measures are covered separately in the project safety plan.
4. OPERATION
- Material:
- Material used will be as approved by the Engineer.
- The sizes and routes routing will be as per the approved Shop Drawings.
- Storage and Protection:
- Deliver components parts to site, completely identified in accordance with shop and certified CAD Drawings prepared for this work.
- Store in accordance with the manufacturer’s instructions, above ground, properly protected from the weather and construction activities.
5. INSTALLATION and fixation
- Pre-Installation:
- All materials and documentation relevant to this particular section of works will be checked and verified ensuring that these are correct and approved type.
- Prior to the commencement of works, ensure that the areas for permanent installation are ready, accessible and in suitable condition.
- Installation:
- No conduit smaller than 20mm in diameter or larger than 32mm diameter shall be used.
- Where a terminal block to be accommodated in the circuit box an extension ring shall be provided.
- Draw-in conduit boxes shall be incorporated at intervals not exceeding:
- Straight run – 10 m.
- Run with four bends – 2.5 m.
- Run with three bends – 5 m.
- Run with one or two bends – 10 m.
- Conduits, which are more than slightly damaged, shall be rejected. Conduits in floors shall be routed and installed so as to avoid the fixings of floor standing equipment to be installed on the floor.
- All joints in PVC conduits, other than screwed joints, shall be cemented with a waterproof adhesive. This adhesive shall be as recommended by the conduit manufacturer.
- Screwed connections between steel conduits and accessories shall be screwed up tight , where coupled by a socket the conduit ends shall butt together; running joints shall be provided with back nuts which shall be screwed up tight.
- PVC conduit shall be saddled at a minimum of 1 meter intervals. All saddles, tubes and boxes must be in perfect alignment to avoid any appearance of warping when the installation is complete. Saddles should not be so tight as to prevent expansion of the conduit.
- Steel conduits run on the surface shall be secured with galvanized saddles spaced not mores than 2 meters apart, on the other hand, a space bar type saddles will NOT be permitted.
- Conduits shall not be run closer than 0.15m to any steam or hot water pipes and shall be run underneath such pipes rather than over them. It should not also be run closer than 0.05m to any telephone, bell or other signaling circuit.
- No wiring or draw-in wires, cables or wire of any description are to be drawn into the conduits until the section of the conduit system involved is complete.
- Drawn-in boxes must be provided to give access to all conduit for the drawing-in or out of any cable after the installation is completed.
- Particular care shall be taken to ensure that no grout or other foreign materials enters the conduit system through joints, or through surface openings. Screw holes in boxes must kept entirely free and clean. After screeding, a compressed air is to be blown through the conduit system to ensure that it is clean and a steel draw wire of adequate size to be pulled through to a certain that no obstructions is adhering to the inside of the conduits.
- Commissioning:
- When conduits are run on shuttering, prior to the laying of concrete insitu, additional security must be provided near to every box and at intervals of not more than 1.2 meters by binding short lengths of steel wire, of not less than 2mm diameter twisted around the conduit and reinforcing steel. The conduits shall be adequately fixed to prevent excessive movement and damage during the pouring and setting of concrete and shall be protected from mechanical damage. Check there is no damage before screed / concrete is poured. Unless otherwise indicated to cast in conduits shall not be less than 30mm.cores to plastered over conduits shall not be less than 5mm.
- Where conduits are left “open ended” prior to wiring they shall be protected by caps or plugs to prevent the ingress of building material.
- All conduits runs must be designed to permit wiring to be readily installed after the complete erection of the conduits through the available draw-in, accessory and luminary suspension boxes.
- Where surface mounted equipment (other than luminaries) is specified, all concealed conduits shall be terminated and an adaptable box installed recessed into the wall at every surface mounted equipment position.
- When conduits are run on shuttering, prior to the laying of concrete insitu, additional security must be provided near to every box and at intervals of not more than 1.2 meters by binding short lengths of steel wire, of not less than 2mm diameter twisted around the conduit and reinforcing steel. The conduits shall be adequately fixed to prevent excessive movement and damage during the pouring and setting of concrete and shall be protected from mechanical damage. Check there is no damage before screed / concrete is poured. Unless otherwise indicated to cast in conduits shall not be less than 30mm.cores to plastered over conduits shall not be less than 5mm.
- Where conduits pass through an external wall/roof the conduit box shall be fitted on the side and after wiring filled with an inert, permanently plastic compound having a high insulation value.
- Make provision in conduit and trunking, installation where building expansion joints are crossed or settlement is likely
- Ensure conduits are not concealed until works has been inspected and approved. Ensure that conduit and fittings buried in concrete or behind plaster are protected against corrosion or electrolytic action prior to rendering.
- Technical Assistance:
- The installation supervising technician for the system trade shall instruct the CONSULTANT Engineer, and Construction Site Manager on the programming and correct operation of the system after the installation is completed.
- This instruction shall be scheduled at the convenience of the staff.
- All such instruction shall be properly recorded.
- WIR will be issued for Consultant approval upon making sure that the installation of the system equipment’s done as per approved shopdrawings and specs and manufacturer recommendations.
6. RESPONSIBILITIES
Ø PROJECT MANAGER
- To ensure that all the preparation and application works are carried out according to the Contract Specification and with the approved drawings.
- To ensure that the progressing of works is carried out according to the planned program and as per the approved method of statement.
- To ensure that all the equipment and material required executing the work are available according to the planned construction program.
- To co-ordinate with the Main contractor, MEP coordinator, Safety Officer for a safe and proper execution of the works.
Ø SITE ENGINEER
- To ensure that the works are carried out according to the Contract Specification, approved method statement and the shop drawings.
- To provide all necessary information and distribute responsibilities to his construction.
- To monitor the progress of work in relation with the work program and to report to the Project Manager.
- To co-ordinate with the safety officer and to ensure that the works are carried out in safe practicing method.
Ø FOREMAN
- The foreman will carry out his duties by maintaining continuous coordination with the site engineer on daily basis, and ensure proper distribution of the work force on the required and planned locations.
- To ensure that his assistant foreman/ charge hand are aware of the job requirements and they have enough information to carry out their duties properly.
- To ensure that the daily work is progressing as planned and advice the site engineer of any requirement for additional resources.
- To ensure in consultation with the site engineer that the manpower involved in the works are moving as agreed and planned for the work.
- To control disposal of waste materials according to the instructions received from the site engineer.
- To ensure full coordination with the safety officer to maintain safe working and proper house keeping of the site, following the proved safety measures and further ensure that all his working team are aware of the same to prevent accident and losses.
- To inform the site engineer regarding areas ready for inspection.
- Foreman and the storekeeper are responsible for the distribution and control of materials.
Ø SAFETY ENGINEER
- Ensure the implementation of all the safety measures in accordance with the HSE plan and everybody aware of it for it’s proper implementation.
- Ensure all the implemented safety measures are adequate to maintain safe working on the site.
- Inspect all the site activities and train the person to prevent accidents and it’s proper implementation.
- Ensure that the site is maintained clean and tidy.
Ø TECHNICIAN FROM SUPPILER
- The carrying-out of work and the proper distribution of all the available resources in coordination with the sub-contractor Site Engineer on a daily basis.
- Daily reports of the works are achieved and coordinated for the future planning with the Site Engineer.
- Complying with the sub-contractor basic design practices, particularly those related to safety and engineering
- Meeting with any type of unforeseen incident or requirement and reporting the same to the Site Engineer immediately.
Ø STORE KEEPER
- Responsible for overall Store operations in making sure to store the material delivery to the site and keep it in suitable area that will keep the material in safe from rusty and damage.
- One who will acknowledge the receiving of materials at site in coordination with QA/QC and concerned Engineer.
7. MANPOWER REQUIRED
- Charge hand and Experienced Technicians
8. MATERIALS REQUIREMENTS
- Electrical Galvanized Conduits Components and Accessories
9. EQUIPMENTs REQUIREMENTs
- The Equipment that will be engaged for Electrical Galvanized Conduits Installation will be as follows:
- Painting Brush
- Measuring tape
- Cutting plier
- Threading Machine
- Box spanner set
- Bending Machine
- Pipe Wrench
- Drilling Machine
- Round files
- Bench vise
- Tripod stand wise
10. WASTE MANAGEMENT
- The Rubbish which would be created from our scope of works will be disposed to the designated dumping ground.
Related: Reviewing Variation Orders in Construction Contracts., Essential Guidelines for Project Stakeholder Management., Factors Contributing to Delays in Engineering, Procurement, Construction, Project Management, and Finance.
11. SPECIAL CONTROL MEASURES
- The following general control measures against Safety, Environment and Quality shall be required for our scope of work and special control measures are not applicable for us :
- Proper PPE must be worn at all time
- Permit to work at height > 2m where applicable
- Lifting operation permit (using crane) where applicable.
- Confined space permit where applicable.
- Approved work method statement and risk assessment will be made available to site.
- All workers doing the work shall be briefed on this method statement and risk assessment.
12. SUPPORTING DOCUMENTATION
- This method Statement should be read in conjunction with the below referenced documentations:
- ITP for Anti – termite Treatment.
- Insulation Resistance and continuity Test Report.
13. DISTRIBUTION
- Copy of this method statement shall be issued to the following for information / action / comments:
- Project Manager
- Site Engineer
- Foremen
- Safety Engineer
- Technician From Supplier
- Store Keeper



