Re-route your Dewatering Line - Construction Template

Dewatering Method Statement

CONTENTS

  1. Scope of Work
  • Definitions
  • References
  • Subcontractors
  • Materials
  • Plant  & Equipment
  • Safety
  • Prior Activities
  • Procedure
  1. Responsibilities
  1. Attachments

1. Scope:

1.1This Method Statement covers the various methods utilized to control water in excavation.
  

2. Definitions:

2.1MS: STM Method Statement : Storm Water Drainage Work
  
2.2ITR    Inspection and Test Request
  
2.3PPS   Particular Project Specification
  
2.4GPS   General Project  Specification
  
2.5UG     Underground
  
2.6TPS   Technical  Project Specification
  

3. References:

3.1TPS    Section 901 :Clause 901.3.3 Pumping and Dewatering

 4. Subcontractors:

 N/A

5.  Products:   

5.1Filter Material (3- 5mm Aggregates)

 6. Tools & Equipments:

6.1Drilling Machine
  
6.2Well Point, header pipes and discharge lines
  
6.3Pumps, hoses and accessories
  

 7. Safety

7.1TPS  Section  : Site Safety and Security
  
7.2CSM Construction Safety Manual
  
7.3OAJ-JV Safety Manual
  
7.4Safety Hazards and Precautions
a.Strike UG  Services:   Use locator and hand excavation (trial holes)
  
b.Excavation Collapse:   Batter sides to safe slope or provide shoring (if required)  
 Keep spoil at least 2.0 meter away from edge
  
c.Fall into Excavation   Provide fencing, guardrails or flagging tape around edges. Provide safely fixed ladders (every 50 meters).  Provide banks man when operating equipment near excavation.

 8. Prior Activities:

8.1A “Dewatering Plan” will be submitted showing typical well points system, sumps, pumps, discharge lines, silt traps and monitoring equipment.  
8.2Earth berms of cut-off ditches will be provided to prevent surface water from entering the excavation where needed.  
  
8.3Proper discharge away from work area will be provided and Permits will be obtained where needed.  
8.5A checking for existing utilities will be conducted before drilling or excavating.

9. Procedure:

A)-   9.1Selection of dewatering method depends on the following :-   Depending on certain factors, one or more of the below detailed dewatering methods can be adopted. The factors affecting the decision include among others:   The soil characteristics   The soil hydrology   The size and depth of the excavation   The proposed method of excavation and ground support   The proximity of existing structure  
B)-Dewatering Method:-
  
9.2Pre-drainage (Well Points System)   Well points will be drilled by augers or high pressure water jet and fitted with riser pipes at sufficient intervals to maintain the surrounding water table below              the level of excavation.
  
 After well points are driven into the ground they are surrounded with a filter layer (5mm sand) to facilitate suction.
  
 Flexible elbows are used to connect the riser pipes to Header pipes, which in turn are connected to suction Pumps.
  
 The water is then pumped through flexible hoses or discharge lines to the discharge points.
  
 Once the water table has sufficiently dropped, the excavation may proceed in dry soil.
  
9.3Open Pump (Sumps)
  
 Excavation continues below the water table and a collection trench and/or pit is dug to one side of the excavation.
  
 Submersible pumps are then utilized to draw off the water and pump it to a discharge area.   
9.4Horizontal Drains  
  Used in conjunction with one of the above mentioned methods.
  Prepare drainage ditches filled with gravel or perforated pipes.                            
  The ditches can be near the trench walls or crossing below the blinding.                             
  

 10. Responsibilities:

10.1It is the Site Manager’s duty to ensure that all necessary safety and protective equipment are provided along with properly trained and qualified personnel.  
10.2It is the Site Supervisor’s duty to organize the work in safe manner and to ensure that safety and protective equipment are being properly utilized. He must also assure the method statement procedure is followed and must observe any hold-points and notify the Consultant for inspection.  
10.3It is the worker’s duty to properly wear the protective equipment provided and obey all safety rules.  They must also perform the work as described in the method statement procedure.  
10.4The Site Engineer will ensure that the site preparation activities are conducted according to the approved method statement.  
10.5The Material Engineer will ensure that the materials being used are in accordance to the project specifications and the approved method statement.  

Related Articles

Related posts:
Method Statement for Surveying Work
Method Statement for Storm Water and Drainage Earthwork

Leave a Comment

Your email address will not be published. Required fields are marked *

Scroll to Top