METHOD STATEMENT FOR DEVICES WIRES INSTALLATION – METHOD STATEMENT FOR Devices Wires installation
METHOD STATEMENT FOR DEVICES WIRES INSTALLATION
nnnn- TABLE OF CONTENTS
1. SCOPE
nnnn2. definitions
nnnn3. HEALTH AND SAFETY
nnnn4. OPERATION
nnnn5. installation and fixation
nnnn6. RESPONSIBILITIES
nnnn7. MANPOWER REQUIRED
nnnn8. MATERIALS REQUIREMENTS
nnnn9. EQUIPMENTs REQUIREMENTs
nnnn10. WASTE MANAGEMENT
nnnn11. SPECIAL CONTROL MEASURES.
nnnn12. SUPPORTING DOCUMENTATION
nnnn13. DISTRIBUTION
nnnn1.SCOPE
nnnn- This procedure to clear the method of the supply, installations of Devices’ Wires for the project.
- This document details Devices’ Wires Installation:
- Preparation of work.
- Delivery and inspection upon arrival of material at site.
- Installation of the system.
2. definitions
nnnnPQP : Project Quality Plan
nnnnPSP : Project Safety Plan
nnnnQCP : Quality Control Procedure
nnnnHSE : Health, Safety and Environment
nnnnMS : Method Statement
nnnnITP : Inspection Test Plan
nnnnQA/QC : Quality Assurance / Quality Control Engineer.
nnnnWIR : Inspection and Test Request
nnnnMIR : Material Verification Record.
nnnn3. HEALTH AND SAFETY
nnnn- Strictly followed as per the manufacturer’s Health and Safety recommendations for handling and use of the materials.
- Ensure all involved personnel shall be aware of the same.
- Specific safety measures have to follow as applicable, and all the safety measures are covered separately in the project safety plan.
4. OPERATION
nnnn- Material:
- Material used will be as approved by the Engineer.
- The sizes and routes routing will be as per the approved Shop Drawings.
- Storage and Protection:
- Deliver components parts to site, completely identified in accordance with shop and certified CAD Drawings prepared for this work.
- Store in accordance with the manufacturer’s instructions, above ground, properly protected from the weather and construction activities.
5. INSTALLATION and fixation
nnnn- Pre-Installation:
- All materials and documentation relevant to this particular section of works will be checked and verified ensuring that these are correct and approved type.
- Prior to the commencement of works, ensure that the areas for permanent installation are ready, accessible and in suitable condition.
- Installation:
- Mark the location of isolator on the walls or ceiling. The mounting height of isolator/disconnect switch in the walls are as follows :
- 15A to 125A isolators mounting height shall be 1400mm A.F.F.L. from the top.
- 200A and above, mounting height shall be 1800mm A.F.F.L. from the top.
- Fix uni-strut channel support on the wall. Ensure that it is fixed properly and rigid.
- Fix the isolator/disconnect switch on the uni-strut channel support. Ensure that it has been fixed vertically and horizontally aligned.
- Terminate the incoming and outgoing feeder cable using appropriate wiring accessories.
- Raise Request for Inspection for isolator/disconnect switches installation.
- Termination:
- Clear all boxes from cement stains and foreign materials.
- Fix wiring accessories ensuring that they are fixed properly and squarely aligned.
- Ensure that the type of wiring devices shall be as approved type as to the areas where they are going to fixed. Ensure that all connections are correct and the wiring devices and boxes shall be earthed.
- Cover all device plates with plastic sheet to protect the wiring accessories.
- Request for Inspection shall be raised for wiring devices installation.
- Technical Assistance:
- The installation supervising technician for the system trade shall instruct the CONSULTANT Engineer, and Construction Site Manager on the programming and correct operation of the system after the installation is completed.
- This instruction shall be scheduled at the convenience of the staff.
- All such instruction shall be properly recorded.
- WIR will be issued for Consultant approval upon making sure that the installation of the system equipment’s done as per approved shopdrawings and specs and manufacturer recommendations.
6. RESPONSIBILITIES
nnnnØ PROJECT MANAGER
nnnn- To ensure that all the preparation and application works are carried out according to the Contract Specification and with the approved drawings.
- To ensure that the progressing of works is carried out according to the planned program and as per the approved method of statement.
- To ensure that all the equipment and material required executing the work are available according to the planned construction program.
- To co-ordinate with the Main contractor, MEP coordinator, Safety Officer for a safe and proper execution of the works.
Ø SITE ENGINEER
nnnn- To ensure that the works are carried out according to the Contract Specification, approved method statement and the shop drawings.
- To provide all necessary information and distribute responsibilities to his construction.
- To monitor the progress of work in relation with the work program and to report to the Project Manager.
- To co-ordinate with the safety officer and to ensure that the works are carried out in safe practicing method.
Ø FOREMAN
nnnn- The foreman will carry out his duties by maintaining continuous coordination with the site engineer on daily basis, and ensure proper distribution of the work force on the required and planned locations.
- To ensure that his assistant foreman/ charge hand are aware of the job requirements and they have enough information to carry out their duties properly.
- To ensure that the daily work is progressing as planned and advice the site engineer of any requirement for additional resources.
- To ensure in consultation with the site engineer that the manpower involved in the works are moving as agreed and planned for the work.
- To control disposal of waste materials according to the instructions received from the site engineer.
- To ensure full coordination with the safety officer to maintain safe working and proper house keeping of the site, following the proved safety measures and further ensure that all his working team are aware of the same to prevent accident and losses.
- To inform the site engineer regarding areas ready for inspection.
- Foreman and the storekeeper are responsible for the distribution and control of materials.
Ø SAFETY ENGINEER
nnnn- Ensure the implementation of all the safety measures in accordance with the HSE plan and everybody aware of it for it’s proper implementation.
- Ensure all the implemented safety measures are adequate to maintain safe working on the site.
- Inspect all the site activities and train the person to prevent accidents and it’s proper implementation.
- Ensure that the site is maintained clean and tidy.
Ø TECHNICIAN FROM SUPPILER
nnnn- The carrying-out of work and the proper distribution of all the available resources in coordination with the sub-contractor Site Engineer on a daily basis.
- Daily reports of the works are achieved and coordinated for the future planning with the Site Engineer.
- Complying with the sub-contractor basic design practices, particularly those related to safety and engineering
- Meeting with any type of unforeseen incident or requirement and reporting the same to the Site Engineer immediately.
Ø STORE KEEPER
nnnn- Responsible for overall Store operations in making sure to store the material delivery to the site and keep it in suitable area that will keep the material in safe from rusty and damage.
- One who will acknowledge the receiving of materials at site in coordination with QA/QC and concerned Engineer.
7. MANPOWER REQUIRED
nnnn- Charge hand and Experienced Technicians
8. MATERIALS REQUIREMENTS
nnnn- Devices’ Wires Components and Accessories
9. EQUIPMENTs REQUIREMENTs
nnnn- The Equipment that will be engaged for Devices’ Wires Installation will be as follows:
- Measuring tape
- Cutting plier
- Box spanner set
- Bending spring
- Pipe Wrench
- Drilling Machine
- Crimping tool
- Screw driver
- Pulling spring
- Hammer
- Common tools
10. WASTE MANAGEMENT
nnnn- The Rubbish which would be created from our scope of works will be disposed to the designated dumping ground.
Related: Reviewing Variation Orders in Construction Contracts., Essential Guidelines for Project Stakeholder Management., Factors Contributing to Delays in Engineering, Procurement, Construction, Project Management, and Finance.
n11. SPECIAL CONTROL MEASURES
nnnn- The following general control measures against Safety, Environment and Quality shall be required for our scope of work and special control measures are not applicable for us :
- Proper PPE must be worn at all time
- Permit to work at height > 2m where applicable
- Lifting operation permit (using crane) where applicable.
- Confined space permit where applicable.
- Approved work method statement and risk assessment will be made available to site.
- All workers doing the work shall be briefed on this method statement and risk assessment.
12. SUPPORTING DOCUMENTATION
nnnn- This method Statement should be read in conjunction with the below referenced documentations:
- ITP for Anti – termite Treatment.
- Insulation Resistance and continuity Test Report.
13. DISTRIBUTION
nnnn- Copy of this method statement shall be issued to the following for information / action / comments:
- Project Manager
- Site Engineer
- Foremen
- Safety Engineer
- Technician From Supplier
- Store Keeper