Contractor’s Letters

CVI

CVI confirmation for false ceiling in a rest room area

Date: xxx Ref: CC/269/CM/83 To                   : M/s. xxx Hotels, Dubai, UAE Kind Attn.     : Mr. xxx Project          : 2B + G + 14+ Lower Roof Hotel Building on Plot No. 373-1297 at Al    Barsha 1st, DubaiU.A.E.      Subject          :   CVI confirmation for false ceiling in a rest room area Dear Sir,  With reference to above we

CVI confirmation for false ceiling in a rest room area Read Post »

cutting the toilet wall tile

Regarding payments for M/S xxx LLC for supplying swimming pool deck tiles

Date: xxx Ref: CC/269/CM/82 To                   : M/s. xxx Hotels, Dubai, UAE Kind Attn.     : Mr. xxx Project          : 2B + G + 14+ Lower Roof Hotel Building on Plot No. 373-1297 at Al    Barsha 1st, DubaiU.A.E.      Subject          :   Regarding payments for M/S Aquazone LLC for supplying swimming pool deck tiles Dear Sir, With reference to

Regarding payments for M/S xxx LLC for supplying swimming pool deck tiles Read Post »

Keys Handing over

Schedule of activity to be completed till date xxx.

Date: xxx Ref: CC/269/CM/81 To                   : M/s. xxx, Dubai, UAE Kind Attn.     : Mr. xxx Project          : 2B + G + 14+ Lower Roof Hotel Building on Plot No. 373-1297 at Al    Barsha 1st, DubaiU.A.E.      Sub                 :   Schedule of activity to be completed till 30/11/2017.     Dear Sir, With reference to above mentioned subject, we

Schedule of activity to be completed till date xxx. Read Post »

Supply of swimming pool deck tiles

Pool Deck Tile Nomination and Verbal Intimation by the Client to Supply the Tile from RAK Project

Date: xxx Ref: CC/269/CM/81 To                   : M/s. xxx, Dubai, UAE Kind Attn.     : Mr. xxx Project          : 2B + G + 14+ Lower Roof Hotel Building on Plot No. 373-1297 at Al    Barsha 1st, DubaiU.A.E.      Sub                 :   Pool Deck Tile Nomination and Verbal Intimation by the Client to Supply the Tile from RAK Project Dear

Pool Deck Tile Nomination and Verbal Intimation by the Client to Supply the Tile from RAK Project Read Post »

Tile

Reconfirmation for tile quantity for typical toilet floor, guest room floor as well as skirting for guest room.

Date                   : xxx Ref                      : CC/269/CM/79 To                       : M/s. xxx, Dubai, UAE Kind Attn.           : Mr. xxx Project          : 2B + G + 14+ Lower Roof Hotel Building on Plot No. 373-1297 at Al    Barsha 1st, Dubai U.A.E. Subject              : Regarding reconfirmation for tile quantity for typical toilet floor, guest room floor as well

Reconfirmation for tile quantity for typical toilet floor, guest room floor as well as skirting for guest room. Read Post »

3-tips-for-Fire-Pump

Request to consider fire pump delivery and installation in July invoice.

Date                   : xxx Ref                      : CC/269/CM/78 To                       : M/s. xxx, Dubai, UAE Kind Attn.           : Mr. xxx Project          : 2B + G + 14+ Lower Roof Hotel Building on Plot No. 373-1297 at Al    Barsha 1st, Dubai U.A.E. Subject              : Request to consider fire pump delivery and i installation in July invoice. Dear Sir,

Request to consider fire pump delivery and installation in July invoice. Read Post »

Kalinga Stone

Regarding Client Interior Informal Inspection on 26th Aug. 2017 for Vanity Counter and Instruction to Modify the Counter

Date                   : xxx Ref                      : CC/269/CM/77 To                       : M/s. xxx, Dubai, UAE Kind Attn           : Mr. xxx Project          : 2B + G + 14+ Lower Roof Hotel Building on Plot No. 373-1297 at Al    Barsha 1st, Dubai U.A.E. Subject              : Regarding  Client Interior Informal Inspection on 26th Aug. 2017 for  Vanity Counter and Instruction

Regarding Client Interior Informal Inspection on 26th Aug. 2017 for Vanity Counter and Instruction to Modify the Counter Read Post »

Wall Cladding

Regarding supply of the tile and without any pre information and without provide any details of the tile.

Date                   : xxx Ref                      : CC/269/CM/75 To                       : M/s. xxx, Dubai, UAE Kind Attn           : Mr. xxx Project          : 2B + G + 14+ Lower Roof Hotel Building on Plot No. 373-1297 at Al    Barsha 1st, Dubai U.A.E. Subject              : Regarding supply of the tile and without any pre information and without provide any

Regarding supply of the tile and without any pre information and without provide any details of the tile. Read Post »

advance payment

Regarding Submission of subcontractor documents xxx Emirates Pre stressed Concrete

Date                   : xxx Ref                      : CC/269/CM/72-1 To                       : M/s. xxx, Dubai, UAE Kind Attn           : Mr. xxx Project          : 2B + G + 14+ Lower Roof Hotel Building on Plot No. 373-1297 at Al    Barsha 1st, Dubai U.A.E. Subject              : Regarding Submission of subcontractor documents VLM Emirates Pre stressed Concrete (including Annexure 01 and

Regarding Submission of subcontractor documents xxx Emirates Pre stressed Concrete Read Post »