Date                   : xxx

Ref                      : CC/269/CM/78

To                       : M/s. xxx, Dubai, UAE

Kind Attn.           : Mr. xxx

Project          : 2B + G + 14+ Lower Roof Hotel Building on Plot No. 373-1297 at Al    Barsha 1st, Dubai U.A.E.

Subject              : Request to consider fire pump delivery and i installation in July invoice.

Dear Sir,

With reference to above mentioned subject, and request that the pump which was delivered in month of July and installed on August 20th 2017.

So, we are requesting kindly approve the same in month of July to release the payment to the supplier.

Related posts:
Reconfirmation for Tile Quantity for Typical Toilet Floor, Guest Room Floor as Well as Skirting for Guest Room.
Pool Deck Tile Nomination and Verbal Intimation by the Client to Supply the Tile from Rak Project

This is for your kind information and request for your consideration.

Thanking you,

For xxx Contracting L.L.C

xxx

Project Manager