Reminder of Our Letter Ref No.CC/HC/018 dated on xxx

shake-up-sales-meeting

Date : xxx Ref no : CC/HC/018 To : M/s xxx Center Attn.             : Mr. xxx Project : 2B + G + 14+ Lower Roof Hotels Building on Plot No. 373-1297 at Barsha,    Dubai Subject : Reminder of Our Letter Ref No.CC/HC/018 dated on 30.05.2018 Dear Mr.xxx, With reference of the above we would… Continue reading Reminder of Our Letter Ref No.CC/HC/018 dated on xxx

Regarding your submitted variation to consultant and find consultant’s reply for your review and re-submission

Undertaking Letter

Date : xxx Ref no : CC/HC/017 To : M/s xxx Center Attn.             : Mr. xxx Project : 2B + G + 14+ Lower Roof Hotels Building on Plot No. 373-1297 at Barsha,    Dubai Subject : Regarding your submitted variation to consultant and find consultant’s reply for your review and re-submission Dear Mr.xxx, With… Continue reading Regarding your submitted variation to consultant and find consultant’s reply for your review and re-submission

Regarding your submission of current invoice and to claim of material delivery

Materials at site

Date: xxx Ref no: CC/HC/016 To                : M/s xxx Center Attn.              : Mr. xxx Project       : 2B + G + 14+ Lower Roof Hotels Building on Plot No. 373-1297 at Barsha,    Dubai Sub                : Regarding your submission of current invoice and to claim of    material delivery                   Dear Mr.Daniel,          With reference to above we… Continue reading Regarding your submission of current invoice and to claim of material delivery

Confirmation to toilet door frame width for single shutter non sliding door area.

toilet door frame width

Date: xxx Ref no: CC/HC/015 To                : M/s xxx Center Attn.             : Mr. xxx Project       : 2B + G + 14+ Lower Roof Hotels Building on Plot No. 373-1297 at Barsha,    Dubai Sub                : Confirmation to toilet door frame width for single shutter non sliding door area. Dear Mr.xxx,          With reference to above… Continue reading Confirmation to toilet door frame width for single shutter non sliding door area.

To provide protective coating for all wood members will be fixed above Ceiling as instructed and required by consultant.

protective coating for all wood

Date: xxx Ref no: CC/HC/014 To                : M/s xxx Center Attn.             : Mr. xxx Project       : 2B + G + 14+ Lower Roof Hotels Building on Plot No. 373-1297 at Barsha,    Dubai Sub                : To provide protective coating for all   wood members will be fixed above Ceiling as instructed and required by consultant. Dear Sir, With… Continue reading To provide protective coating for all wood members will be fixed above Ceiling as instructed and required by consultant.

Regarding your measurement sheet & discrepancy and our concern.

CVI

Date: xxx Ref no: CC/HC/013 To               : M/s xxx Center Attn.            : Mr. xxx Project       : 2B + G + 14+ Lower Roof Hotels Building on Plot No. 373-1297 at Barsha,    Dubai  Sub               : Regarding your measurement sheet & discrepancy and our concern. Dear Sir, With reference to above, we would like to seek… Continue reading Regarding your measurement sheet & discrepancy and our concern.

Regarding your mail reference dated on xxx

subcontractor contract agreement.

Date: xxx Ref no: CC/HC/012 To               : M/s xxx Center Attn.           : Mr. xxx   Project      : 2B + G + 14+ Lower Roof Hotels Building on Plot No. 373-1297 at Barsha,    Dubai  Subject       : Regarding your mail reference dated on 18/09/17 @ 9.54 AM.  Article-A- Attachment page no 1/7 HC -Initially the Architrave… Continue reading Regarding your mail reference dated on xxx

Regarding Non Compliance Report by reducing the architrave size and not matching with approved drawing

fixing doors

Date: xxx Ref no: CC/HC/011 To             : M/s xxx Center Attn.         : Mr. xxx   Project     : 2B + G + 14+ Lower Roof Hotels Building on Plot No. 373-1297 at Barsha,    Dubai  Subject    : Regarding Non Compliance Report by reducing the architrave size and not matching with approved drawing. Dear Sir, With reference… Continue reading Regarding Non Compliance Report by reducing the architrave size and not matching with approved drawing

Regarding non submission of advance payment invoice and bank guaranty against advance payment.

Advance-Payment-Bank-Guarantee

Date: xxx Ref no: CC/HC/010 To             : M/s xxx Center Attn.         : Mr. xxx   Project     : 2B + G + 14+ Lower Roof Hotels Building on Plot No. 373-1297 at Barsha,    Dubai  Subject   : Regarding non submission of advance payment invoice and bank guaranty against advance payment. Dear Sir, With reference to the… Continue reading Regarding non submission of advance payment invoice and bank guaranty against advance payment.

To provide clearance for the False ceiling work in guest room passage in typical floor. (Mock up room)

False ceiling work

Date: xxx Ref no: CC/HC/009 To             : M/s xxx Center Attn          : Mr. xxx   Project     : 2B + G + 14+ Lower Roof Hotels Building on Plot No. 373-1297 at Barsha,    Dubai  Subject       : To provide clearance for the False ceiling work in guest room passage in   typical floor. (Mock up room) Dear… Continue reading To provide clearance for the False ceiling work in guest room passage in typical floor. (Mock up room)