Keys Handing over

Taking-Over Certificate (Preliminary Handing Over)

M/s xxx Pojects Co.

P.O. Box xxx, Riyadh, K.S.A

Tel : xxx

Fax: xxx

Attention:       Mr. xxx

                        Chief Executive Officer

Cc:                  Eng. xxx

                        Sr. Project Engineer

                        Eng. xxx

                        Project Manager

Project:          xxx Project -KSA      

Subject:        Taking-Over Certificate (Preliminary Handing Over )          

Dear Sir,

Further to our Subcontract Agreement reference xxx dated 16th July xxx regarding the Supply, Fabrication and Installation of Built-in and Loose Furniture for Water Villas and Family Units of the above-mentioned project, and after having completed our Subcontract Works, we hereby request for the issuance of the Taking-Over Certificate (Preliminary Handing Over) in accordance with Article 124 of the Subcontract Agreement.

Furthermore, we also confirm that we will attend to any defective works that may arise during the maintenance period of 400 days, upon receipt of a written notice from your end.

This is for your information and necessary action.

Best Regards,

For: Xxx(Name of the Sub-Contractor) Interiors L.L.C.

xxx

Commercial Manager             

Leave a Comment

Your email address will not be published. Required fields are marked *

Scroll to Top