Letter Ref. xxx
Date: xxx
M/s xxx
P. O. Box xxx, Doha, Qatar
T. xxx
E. xxx
Attention : Ms. xxxx
Technical Manager
Project : xxx Qatar
Subject : Notice of Delay – Tower 16A
Dear Sir,
We refer to our ongoing works on the above referred project; we would like to draw your attention regarding our inability to start the installation of Kitchen due to the following;
- MEP Testing & Commissioning not yet completed
- All the ceiling works have to be completed prior to the installation.
- Ceilings are to be closed prior to Kitchen Installation.
- All Wall Tiling Works shall be completed prior to installation.
- All defected floor tiles to be replace.
- All the drainage and electrical points which affect the Kitchen Cabinets area to be rectified.
- At least first coat of paint to be applied to walls and ceiling
- At least main door for each flat to be installed with accessories.
Please be informed that any delays in completing the above referred activities which will delay our progress of works shall not be our responsibility, we reserve our rights for extension of time of completion.
This is for your information and necessary action.
Sincerely yours,
For Xxx (Name of the Subcontractor) Interiors LLC
xxx
Commercial Manager