M/s xxx Building Contracting LLC
PO Box xxx, Dubai, U.A.E
T: xxx | F: xxx
Email: xxx
Attention : MR. xxx
Project Manager
Project : xxx Sky Tower – Umm Ramool
Subject : Letter of Undertaking
Dear Sir,
We, Xxx (Name of the Subcontractor) Interiors LLC hereby undertake to carry out and finish with due expedition any outstanding work under the Work Order reference xxx dated 27th May xxx which we signed with M/s ASCON, that will be required during the Defects Liability Period which shall commence upon the date as specified in the Taking-Over Certificate.
This letter of undertaking is limited to the defects in manufacturing and workmanship, and it does not cover any defects caused by any third party, defects due to normal wear and tear and abuse of use.
We agree to mobilize our team upon receipt of a written notice from the Engineer and/or Client.
Sincerely Yours,
For Xxx (Name of the Subcontractor) Interiors LLC
xxx
Commercial Manager