M/s xxx Constructions and Operations
Office No,. xxx,
Financial Tower, DIFC xxx
Tel: xxx
Fax: xxx
Attention : Mr. xxx
Project Manager
Project : xxx – 6B+G100 Floors-Hotel & Residential Tower
Client : M/s xxx Holdings Ltd
Consultant : M/s xxx Architectural & Engineering Consultants
Subject: Damaged Installed Door
Dear Mr. Ibrahim,
We would like to draw your attention regarding the damaged done by other Subcontractors on our installed wooden door where they have used wooden wedges in order to keep the door remained open (refer to the attached photos).
Please be informed that we reserve our rights to claim for additional cost for the required rectification of the damaged door and the relevant details will be submitted in due course.
We request xxx to advice other subcontractors to refrain from damaging the works of other such as the joinery works.
This is for your information and necessary action.
Kind Regards,
For xxx Interiors LLC
xxx
Project Manager