M/s xxx Constructions and Operations
Office No,. xxx,
Financial Tower, DIFC xxx
Tel: xxx
Fax: xxx
Attention : Mr. xxx
Project Manager
Project : xxx – 6B+G100 Floors-Hotel & Residential Tower
Client : M/s xxx Holdings Ltd
Consultant : M/s xxx Architectural & Engineering Consultants)
Subject : SITE CONDITION – 52nd & 54th FLOORS
Dear Sir,
We would like to bring to your kind attention that the site is not yet ready to receive our materials for installation on the 52nd and 54th floors. Please see the attached photos for your reference. Nevertheless, we have already delivered our materials on site. With this, we kindly request you to do the needful at the earliest.
The same is for your information and necessary action.
Kind Regards,
For xxx Interiors LLC
xxx
Project Manager