TABLE OF CONTENTS
- Purpose
- Scope of Work
- Definitions
- References
- Materials
- Tools, Plant & Equipment
- Safety
- Prior Activities
- Procedure
- Responsibilities
- Attachments
- Purpose
1.1 To ensure that the backfilling of building structures is executed safely and in accordance with the contract requirements and that all quality assurance/ control activities are conducted in a systematic manner, works are inspected and conformance is verified and documented.
- Scope of Work
- This procedure is applicable to the following works associated with the Project titled, “New 2K Runway – Main Runway Works” – Contract Number NRTW-1008-CN.
- This method statement outlines the procedures to be followed in the backfilling of building structures.
- Definitions
- CM Construction Manager
- SE Site Engineer
- CS Chief Surveyor
- ME Material Engineer
- ESHO Environmental, Safety, and Health Officer
- ITP Inspection Testing Plan
- AHA Activity Hazard Analysis
- JHA Job Hazard Analysis
- References
- Specifications: Volume 3 – Section 9 – Part A – General, Civil and Mechanical Infrastructure
- Drawings: Volume 2 – Section 8 – Part D
- BOQ: Bills 12, 13, 14, 15, 16 & 17
- Material
- Suitable fill ( approved Selected Excavated Materials )
- Water
- Warning Tapes
- Safety Barrier
- Traffic Cones
- Tools, Plant & Equipments:
- Wheel loader
- Dumper truck
- Water tanker
- Cylinder Compactor
- Plate compactor
- Hand tamping tools
- Personal Protective Equipment
- Safety
- Prior to the commencement of any activities, the workforce will receive an induction talk on the project site safety requirements. This induction talk will include both activity safety issues, as well as general safety requirements.
- Front line supervisor will ensure that Personal Protective Equipment is worn by site personnel at all times during construction activities.
- Heat Stress Training will be provided.
- Adequate cool drinking water, shade, and salt water tablets will be in place.
- Plant and Equipment will be provided with back-up alarms, lights, and all other applicable safety devices.
- For AOA work, safety requirements as defined per Section 107 will be implemented. Specific safety training will be provided to personnel for AOA work.
- Prior Activities
- Final approval for the waterproofing system should be obtained from the Engineer through the checking requests before commencement of any backfilling works.
- Procedure
- The suitable fill shall be delivered to the backfilling location by dumper trucks.
- The suitable fill shall be spread by wheel loader and labourers. It shall be then compacted by using plate and cylinder compactors.
- Backfilling material shall be compacted to 95% MDD in 200mm lifts.
- Extreme care shall be taken to avoid any damage to the waterproofing system of the structures during the back filling operation .
- Responsibilities
- The CM will coordinate with SE and ensure that necessary resources to implement the approved method statement, JHA, and AHA have been allocated to the task.
- The SE will ensure that the site preparation activities are conducted according to the approved method statement, JHA and AHA. The SE will also ensure that all in-situ tests, as required by the ITP, are implemented.
- The ME will ensure that the materials being used are in accordance with the project specifications and the approved material submittals.
- It is the site supervisor’s responsibility to organize the work in a safe manner to ensure that safety and protective equipment are being properly utilized. He must also ensure that the AHA and JHA are implemented and the approved method statement procedure is followed and the ITP is applied.