Approval and Finalization

Items to Be Finalize by Consultant and Client

Date: 10th March 2020

Ref.: xxx/1001/AEC/019/2020

Total Pages: 1

To,

M/s. xxx Architects &Engineers

P.O. Box: xxx, Dubai, UAE.

Phone: +971 xxx

Attention        :           Mr.  xxx – Architect

Project           :           Proposed G+1 Villa On plot No. xxx at Al Barsha South

            Second, Dubai – U.A.E for Mr. xxx

Subject:           Items to Be Finalize by Consultant/Client

Dear Sir,

With reference to the aforementioned subject, we would like to draw your attention on the following pending which may impede project completion as per agreed baseline program.

Sl. NoItems particularImpacted Activities
1Internal stair steps stoneCompletion of floor tiles.
2External Flooring Stone and Step StoneErection of scaffolding, External painting works
3Shower Glass Partition Subcontractor 
4SkylightCompletion of Aluminum and Glazing works
5Garage Door Subcontractor 
6Pedestrian Gate Subcontractor 
7Cat Ladder Subcontractor 
8Toilet stone sinkFixing of Mirrors and sanitary ware
9Mirror 
10Swimming Pool WorksPerformance of swimming pool subcontractor is extremely poor and slow, expecting your intervention.
11Vanity counterFixing of stone sink, sanitary ware, and mirrors.
12Kitchen CabinetFixing of sanitary ware
13Wardrobes 
14Aluminum and glazing worksWooden joinery works, painting works

This is for your kind immediate action.

Thank You

Yours Sincerely,

Xxx Building Contracting LLC