Date: 10th March 2020
Ref.: xxx/1001/AEC/019/2020
Total Pages: 1
To,
M/s. xxx Architects &Engineers
P.O. Box: xxx, Dubai, UAE.
Phone: +971 xxx
Attention : Mr. xxx – Architect
Project : Proposed G+1 Villa On plot No. xxx at Al Barsha South
Second, Dubai – U.A.E for Mr. xxx
Subject: Items to Be Finalize by Consultant/Client
Dear Sir,
With reference to the aforementioned subject, we would like to draw your attention on the following pending which may impede project completion as per agreed baseline program.
| Sl. No | Items particular | Impacted Activities |
| 1 | Internal stair steps stone | Completion of floor tiles. |
| 2 | External Flooring Stone and Step Stone | Erection of scaffolding, External painting works |
| 3 | Shower Glass Partition Subcontractor | |
| 4 | Skylight | Completion of Aluminum and Glazing works |
| 5 | Garage Door Subcontractor | |
| 6 | Pedestrian Gate Subcontractor | |
| 7 | Cat Ladder Subcontractor | |
| 8 | Toilet stone sink | Fixing of Mirrors and sanitary ware |
| 9 | Mirror | |
| 10 | Swimming Pool Works | Performance of swimming pool subcontractor is extremely poor and slow, expecting your intervention. |
| 11 | Vanity counter | Fixing of stone sink, sanitary ware, and mirrors. |
| 12 | Kitchen Cabinet | Fixing of sanitary ware |
| 13 | Wardrobes | |
| 14 | Aluminum and glazing works | Wooden joinery works, painting works |
This is for your kind immediate action.
Thank You
Yours Sincerely,
Xxx Building Contracting LLC