Date: 10th March 2020
Ref.: xxx/1001/AEC/019/2020
Total Pages: 1
To,
M/s. xxx Architects &Engineers
P.O. Box: xxx, Dubai, UAE.
Phone: +971 xxx
Attention : Mr. xxx – Architect
Project : Proposed G+1 Villa On plot No. xxx at Al Barsha South
Second, Dubai – U.A.E for Mr. xxx
Subject: Items to Be Finalize by Consultant/Client
Dear Sir,
With reference to the aforementioned subject, we would like to draw your attention on the following pending which may impede project completion as per agreed baseline program.
Sl. No | Items particular | Impacted Activities |
1 | Internal stair steps stone | Completion of floor tiles. |
2 | External Flooring Stone and Step Stone | Erection of scaffolding, External painting works |
3 | Shower Glass Partition Subcontractor | |
4 | Skylight | Completion of Aluminum and Glazing works |
5 | Garage Door Subcontractor | |
6 | Pedestrian Gate Subcontractor | |
7 | Cat Ladder Subcontractor | |
8 | Toilet stone sink | Fixing of Mirrors and sanitary ware |
9 | Mirror | |
10 | Swimming Pool Works | Performance of swimming pool subcontractor is extremely poor and slow, expecting your intervention. |
11 | Vanity counter | Fixing of stone sink, sanitary ware, and mirrors. |
12 | Kitchen Cabinet | Fixing of sanitary ware |
13 | Wardrobes | |
14 | Aluminum and glazing works | Wooden joinery works, painting works |
This is for your kind immediate action.
Thank You
Yours Sincerely,
Xxx Building Contracting LLC