Date: xxx
Ref: xxx
Kind Attn :Mr. xxx
Project: 2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai
Subject : Variation for Raised floor and Epoxy Coating in GSM Room at 14th Floor as required by CADDEMIRATES Subcontractor.
Dear Sir,
With reference to above and mail communication (dated xxx) received from Prashant Hegde (PM of xxx Emirates) for server room at 14th Floor, they required the below mentioned scope which is additional scope for the main contractor. Details mentioned below along with BOQ Cost:
Sl No | ITEM DESCRIPTION IN NOMINATION | CONTRACT BOQ ITEM REF | QTY | UNIT | RATE (AED/unit) | TOTAL (AED) |
1. | Supply and fixing of raised floor in GSM Room at 14th Floor. (Size: 4.39m x 3m = 13.17sqm) | Bill No 10/4/14 Item no: A Pg No. 5/7 | 13.17 | Sqm | 150 | 1,975.50 |
2. | Supply and application of Epoxy Coating in GSM Room at 14th Floor. (Size: 4.39m x 3m = 13.17sqm) | Bill No 10/1/14 Item no: B Pg No. 4/7 | 13.17 | Sqm | 55 | 724.35 |
SUB-TOTAL | 2,699.85 | |||||
VAT (5%) | 134.99 | |||||
TOTAL (TWO THOUSAND EIGHT HUNDRED THIRTY FOUR DIRHAMS AND EIGHTY FOUR FILS ONLY) | 2834.84 |
Attachment list:
1) Mail Communication with Prashant Hegde (dated 16/03/18)
2) BOQ Page 10/1/14 for Epoxy Coating Rate (Item B)
3) BOQ Page 10/4/14 for Epoxy Coating Rate (Item A)
4) Revised Drawing of 14th Floor Plan
5) Approved Drawing of 14th Floor Plan
So, this is for your kind intimation and instruction awaited and the additional scope required additional time and cost to execute.
Regards,
For xxx Contracting L.L.C.