Date: xxx
Ref: xxx
Kind Attn :Mr. xxx
Project: 2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai
Project : 2B + G + 14+ Lower Roof Hotels Building on Plot No. 373-1297 at Barsha,Dubai
Sub : Regarding CCTV camera drawing approval from Dubai police.
Dear Sir
With reference to above, we would like to inform you that till date no sub contractor appointment for CCTV camera for the project and we do not have approved drawing from Dubai police.
Please note that we can pull the wire till we do it have approved drawing from Dubai police for camera location and formal approval.
Kindly do needful it have impact in false ceiling as well as external work which is already in progress.
Regards,
For xxx Contracting L.L.C.
xxx
Project Manager