Bathtub overflow fittings rejection by consultant

Date:               xxx

Ref:                  xxx

Kind Attn         :Mr. xxx

Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai

   Subject        : Regarding Bathtub overflow fittings deliverd by STstyle LLC on xxx and inspection rejection by consultant.

Dear Sir,

With reference to above, the Bathtub fittings material delivery by the client soupier named STstyle on 27th August xxx and we raised the material inspection CEM/MI/269/63 dtd on 28th August xxx and the inspection report attached here with comments “not approved”.

So, this is for your kind information that we canot use the fittings as inspection rejected by the consultant and we canot fix the Bathtub in mock up floor as well as other floor till the fiiting issue will not resolve.

Regards,

For xxx Contracting L.L.C.

xxx

Project Manager