Date: xxx
Ref. xxx
To : M/s. xxx Technical Service LLC.
Kind Att : Mr. xxx Kumar
Project : 2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at
Al Barsha 1st, Dubai, U.A.E.
Subject : Removal of Roadside Scaffolding
Dear Sir,
With reference to the above mentioned subject, we are hereby intimating you that we are removing the roadside scaffolding since RTA will start the external interlock and Dubai Municipality will execute the drainage connection because we are holding the authority to complete your work and now we cannot stop them to execute their work to complete the project as we have given 10 days by Dubai Municipality to clear the area.
So, we are informing you that we will remove the road scaffolding and you are allowed to use cradle.
terms and conditions in the contract dated 07/09/2017 will remain the same.
Thanking you,
For xxxx Contracting L.L.C
xxx
Project Manager: