Delay in Nomination 2 - Construction Template

Delay in Nomination 2 – Nomination of Provisional Sum

n

Date: xxx

Nomination of Provisional Sum

n

About Delay in Nomination 2

nnn

Ref.: xxx

nnnn

Total Pages: 1

nnnn

To,

nnnn

xxx

nnnn

Attention:      xxx

nnnn

Project:          xxx.

nnnn

Subject:           Delay in Nomination of Provisional Sum & Prime Cost Subcontractors

nnnn

Reference:       MCM/AAZ/OCAC/04/2019 dated 26th November 2019

nnnn

                        MCM/AAZ/OCAC/05/2019 Reminder -1 dated 8th December 2019

nnnn

MCM/AAZ/OCAC/05/2019 dated 24th December 2019

nnnn

MCM/AAZ/OCAC/07/2019 dated 6th January 2020

nnnn

Dear Sir,

nnnn

With reference to above cited letters, we wish to put on record there has been a significant delay in nomination of provisional items and selection of Prime Cost Items. The delay in nomination and selection will affect the project critical path and delay the overall project completion. Following are the Provisional Sum items to be nominated by Client and Prime Cost Items list are attached.

nnnn
Sl. No.BOQ Ref.Item ParticularImpacted ActivitiesRemarks
1BOQ REF. 3/50/GSwimming Pool WorksApproval of Shop Drawing, Materials. Submission of LV Load schedule to DEWA. 
2BOQ REF. 4/52/AHVAC Air Conditioning WorksBuilders Works, Approval of HVAC Shop Drawing, Materials, RCP and MEP Coordination Shop Drawing. Submission of LV Load schedule to DEWA. 
3BOQ REF. 5/8Light Fighting SupplierSubmission of LV Load schedule to DEWA. 
4BOQ REF. 5/9Switch and Socket Supplier  
nnnn

Upon receipt of subcontractor/supplier nomination MCM will enter a subcontracting agreement/ issue LPO, the next step will be securing Engineer approval for shop drawing and materials. Once required approval are secured then only materials delivery lead time will be started. Depend upon selection of materials the lead time may vary 4 weeks to 14 weeks. Considering said scenario Provisional Sum and Prime cost subcontractor/supplier nomination are extreme critical at current stage to complete the project as agreed completion time.

nnnn

The Contractor reserve its right pursuant to Sub-Clause 6.3, 44.1(d) and 53.1 of Condition of contract to claim time and cost implication due to delay in nomination of provisional sum and prime cost subcontractor/supplier.

nnnn

Therefore, we request your urgent intervention to address this matter by asking to the Client to finalize the pending nominations on top priority basis.

nnnn

Thank You

nnnn

Yours Sincerely

nnn

Related: Biography of Greatest Actress Doris Day, Biography of Greatest Actress Giulietta Masina, Biography of Greatest Actress Victoria Abril

n

XXX

n { “@context”: “https://schema.org”, “@type”: “Article”, “headline”: “Delay in Nomination 2 – Nomination of Provisional Sum”, “description”: “Nomination of Provisional Sum: we wish to put on record there has been a significant delay in nomination of provisional items and selection of Prime Cost I”, “author”: { “@type”: “Person”, “name”: “Md Abu Zaed Khan” }, “datePublished”: “2020-12-20T13:09:43+04:00”, “dateModified”: “2026-06-17T08:42:45+04:00”, “url”: “https://engineersblog.net/nomination-of-provisional-sum/” } { “@context”: “https://schema.org”, “@type”: “BreadcrumbList”, “itemListElement”: [ { “@type”: “ListItem”, “position”: 1, “name”: “Home”, “item”: “https://engineersblog.net/” }, { “@type”: “ListItem”, “position”: 2, “name”: “Contractor’s Letters”, “item”: “https://engineersblog.net/contractors-letters/” }, { “@type”: “ListItem”, “position”: 3, “name”: “Delay in Nomination 2 – Nomination of Provisional Sum”, “item”: “https://engineersblog.net/nomination-of-provisional-sum/” } ] }