To fix the floor tile in first floor corridor outside of All Day Dining
Date : xxx
Ref : xxx
To : M/s. xxx GROUP, PO Box xxx, Sharjah UAE.
Project : 2B + G + 14 + Lower Roof Hotels Building on Plot No. xxx at Barsha, Dubai
Subject | : | To fix the floor tile in first floor corridor outside of All Day Dining |
Dear Mr.xxx,
With reference to the above, we have issued variation work to fix the tile/ continue from All Day Dining area to consider/passage.
So, up to how you didn’t execute the scope and variation instruction issued to you by client long before.
Kindly do needful as soon as possible and acknowledge the same.
Regards,
For xxx Contracting L.L.C
xxx
Project Manager
Md Abu Zaed Khan