Revised Drawing and your Document Transmittal Ref No. xxx dated xxx

Revised Drawing and your Document Transmittal Ref No. xxx dated xxx

Date: xxx

Ref. xxx

To:

M/s. xxx Consulting Architects and Engineers

Dubai, UAE

Kind Attn:     Mr. xxx

Project:          2B + G + 14+ Lower Roof Hotels Building on Plot No. xxx at Barsha, Dubai.

Subject:             Revised Drawing and your Document Transmittal Ref No. xxx dated xxx

Dear Sir,

               With reference to the above subject, we have received the revised drawing as per above mention reference no. and date. Kindly note the following:

  1. It is simply the document transfer without any comment/special instruction, either for the Action/Information/Record.
  2. As we verbally discuss and you confirm that this revised architectural drawing needs to be executed at site and we must make necessary change in approved structural drawing as well as needs to be submitted for your approval.
  3. We already instructed the MEP contractor to revise the MEP Drawings as per this change.
  4. We will analyze the impact in all respect and will be intimated accordingly.
  5. Our kind request that any revision in the drawing should be released through your site office only with the covering letter since this is the changed in the approved document. 

This is for your record and information.

Regards,

For xxx Contracting L.L.C

xxx

Project Manager