Date: XXX
CC/SCHINDLER/002
To : M/s XXX Intl.Ltd
Project : 2B + G + 14 + Lower Roof Hotels Building, Plot No. XXX at Al Barsha 1st, Dubai
Subject : Regarding Dumb Waiter Co-ordination and Handing Over
Dear Sir,
With reference to the above mentioned subject, we have given you numerous calls for the dumb waiter handing over. Even we are calling your sub-contractor, neither you or your sub-contractor is not serious to hand over. We have the following issues which please note:
- Dumb waiter has not been handed over till date.
- The Consultant rejected the inspection because of the many issues for the finishing and we intimated you many times through phone.
So, kindly do the needful as soon as possible time as you are also delaying our other sub-contractor.
Regards,
For XXX Contracting L.L.C
XXX
General Manager