Regarding Hiring the subcontractor for cementitious work and cleaning as well as providing confirmation that agreement for the steel work is null and void.

Date: 13.11.2016 Ref no: CC/DT/DM/0013 To, Dubai Municipality Building Control section Dubai, UAE Project      : 2B+G+7+Gym Residential building at Culture Village, Al Jadaf Sub            :  Regarding  Hiring the subcontractor for cementitious work and cleaning  as well as providing confirmation that agreement for the steel work is null and void. Dear Sir, With reference to the above, we would like to inform […]

GATE PASS

GATE PASS DATE: 02.11.2016 PROJECT SITE: 2B+G+14+Lower Roof Hotel Building Plot No.: 373-1297 Location: Al Barsha 1st, Dubai UAE DESCRIPTION: ______________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________ Send To: Driver Name:Mazan Khan Vehicle No.:89787 REMARKS: __________________________________________________________________________________________________________________________________________________________________________________________________________________________________________ Received By: _________________________                        Checked By: __________________

Regarding Confirmation for concrete strength and durability due to change of the slump value to 200+- 25mm and 2 hour pouring time

Date:               20.11.2016 Ref:                  To                   : Project           : 2B + G + 14+ Lower Roof Hotels Building on Plot No. 373-1297 at Barsha, Dubai Subject          : Regarding Confirmation for concrete strength and door ability due to change of the slump value to 200+- 25mm and 2 hour pouring time Dear Sir, With reference to the above, we are hereby […]

Delay in the certification of our invoice and notice for the delay of the project due to non-payment

Date: 13.10.16 Ref:    CC/EM2/MRP004/13 Kind Attn:   Mr.xxx Khan             Project:      B+G+4 Residential Building on Plot no: JVC 151MRPxxx at Jumeriah Village Circle Client:       M/s xxx Limited       Subject:    Delay in the certification of our invoice and notice for the delay of the project due to non-payment Dear Sir, With reference to above, we have submitted our invoice on 31st August, 2016 […]

Undertaking letter by Main contractor for structural safety /building safety as required in application no: xxx-23-1.

Date: 09.11.216 Ref no: CC/DT/DM/09 To, Dubai Municipality Building permit section Dubai, UAE Project       :    2B + G + 14+ Lower Roof Hotels Building on Plot No. 373-1297       at Barsha, Dubai Sub      :  Undertaking letter by Main contractor for structural safety /building    safety as  required in application no:241570-23-1. Dear Sir, With reference to the above, we the main contractor […]

Engineers are ready for training required for xxx Contracting L.L.C

Date: xxx Ref no: CC/DT/DM/06/16-1 To The Manager, DM Qualification Section (License) Dubai Municipality, Dubai UAE Sub:  Engineers are ready for training required for xxx Contracting L.L.C License no: xxx Dear Sir, With ref. to above and requirement our engineers are ready to take the training immediately with your appointment. So, kindly provide immediate appointment to attend the same for […]

Clearance from MEP Section

Date: 24.12.16 To, Mr. xxx Project        : 2B + G + 14+ Lower Roof Hotels Building on Plot No. 373-1297 at Barsha, Dubai Sub            :  Clearance from MEP Section Dear All, With reference to the above, you are all required to get a clearance from MEP department to prevent double work with regards for any plaster works. If you failed […]

Instructions for Duties

Date: 24.12.16 To, Mr. xxx Project        : 2B + G + 14+ Lower Roof Hotels Building on Plot No. 373-1297 at Barsha, Dubai Sub            :  Instructions for Duties Dear Viqar, With reference to the above, below are the planning lists of your duties for your reference. As per plan of R9 you should input the daily resources as per WBS […]

MONTHLY PROGRESS REPORT

                                      MONTHLY PROGRESS REPORT NO. 13                                                      Month Ending 30th of September 2016                 Project No                   :         xxx                 Project Title                :         2B+GF+14 Floors+ Lower Roof Hotel Building                 Client                          :         xxx                                       Consultant                   :         xxxx Consulting Architechs & Engineers                                       Contractor                  :         xxx Contracting L.L.C. Table of Contents: Executive Summary…………………………………………………………………Section 1 Progress Report………………………………………………………………………Section […]