MONTHLY PROGRESS REPORT - Construction Template

Monthly Progress Report

n

                                      MONTHLY PROGRESS REPORT NO. 13

MONTHLY PROGRESS REPORT

n

About Monthly Progress Report

nnn

                                                     Month Ending 30th of September 2016

nnnn

                Project No                   :         xxx

nnnn

                Project Title                :         2B+GF+14 Floors+ Lower Roof Hotel Building

nnnn

                Client                          :         xxx

nnnn

                                      Consultant                   :         xxxx Consulting Architechs & Engineers

nnnn

                                      Contractor                  :         xxx Contracting L.L.C.

nnnn

Table of Contents:

nnnn

Executive Summary…………………………………………………………………Section 1

nnnn

Progress Report………………………………………………………………………Section 2

nnnn

List of Equipment………………………………………………………………….            ..Section 3

nnnn

Record of Manpower…………………………………………………………………Section 4

nnnn

Requirement of Subcontractors / Suppliers …………………………………………Section 5

nnnn

Material Submittal Log………………………………………………………………Section 6

nnnn

Shop Drawing Submittal Log………………………………………………………. Section 7

nnnn

RFI Log………………………………………………………………………………Section 8

nnnn

Inspection Request Report Log………………………………………………….….Section 9

nnnn

Method Statement Log………….…………………………………………………..Section 10

nnnn

Procurement Log-Long Lead Items………………………………………………… Section 11

nnnn
  1. Procurement Log PC Items
  2. Procurement Log PS Items
  3. Procurement Log on Long Lead Item
nnnn

Progress Photos…………………………………………………………………….            Section 12

nnnn

HSE Report…………………………………………………………………………            Section 13

nnnn

Section 1

nnnn

EXECUTIVE SUMMARY

nnnn
  1. Executive Summary
nnnn

Project Name                   :           2B + GF + 14 Floors + Lower Roof Hotel Building   

nnnn

Project Location             :           Plot No. xxx Al Barsha Dubai, UAE

nnnn

Client                               :           xxx

nnnn

Lead Consultant             :           xxx Consulting Architects & Engineers

nnnn

Project Value                   :           AED: 33,000,000.00

nnnn

Commencement Date     :           09th September 2015

nnnn

Project Finish                  :           08th January 2017

nnnn

Project Duration             :           488 days including mobilization

nnnn

Built up Area                   :           1,025 m²

nnnn

Project Information:

nnnn

The scope of works for the 2B + GF + 14 Floors + Lower Roof Hotel Building consist of the following site works;

nnnn
  1. Substructure foundation, reinforced in –situ concrete frame comprising ground floor plus floors, with roof level and services blocks.
nnnn
  1. Internal and external finishes inclusive of waterproofing, insulation, supply and installation of doors and windows and all equipment and facilities identified in the Contract documents.
nnnn
  1. The installation of Electro Mechanical Works inclusive of testing and commissioning
nnnn
  1. External Works finishing as per specification & Drawings
nnnn

Overall Progress

nnnn

Mobilization                           :           100%

nnnn

Contract duration                    :           488 days

nnnn

Time elapsed                          :           386 days   –   79.09%

nnnn

Time left                                 :           102 days   –   20.99 %

nnnn

Location of plot                      :           Plot No. 373-1297 Al Barsha Dubai

nnnn

Plot Area                                 :           1025 m²

nnnn

Total GFA                               :           550 m²

nnnn

Section 2

nnnn

PROGRESS REPORT

nnnn

PROGRESS REPORT

nnnn
AREAACTIVITYCOMPLETED
GROUND FLOOR TO                    FIRST FLOORReinforcement & Shutter  for Columns100%
Reinforcement & Shutter for RC Walls100%
Reinforcement & Shutter for Retaining Walls100%
Pouring of Concrete for Columns100%
Pouring of Concrete for Retaining Wall100%
Pouring of Concrete for RC Walls100%
First Floor PT Slab & Beam Shuttering100%
First Floor PT Slab & Beam Reinforcement100%
Casting of First Floor PT Slab & Beam100%
nnnn
AREAACTIVITYCOMPLETED
FIRST FLOOR      TO               SECOND FLOORReinforcement & Shutter  for Columns100%
Reinforcement & Shutter for RC Walls100%
Reinforcement & Shutter for Retaining Walls100%
Pouring of Concrete for Columns100%
Pouring of Concrete for Retaining Wall100%
Pouring of Concrete for RC Walls100%
Second Floor PT Slab & Beam Shuttering95%
Second Floor PT Slab & Beam Reinforcement95%
Casting of Second Floor PT Slab & Beam100%
nnnn
AREAACTIVITYCOMPLETED
SECOND FLOOR      TO  THIRD  FLOORReinforcement & Shutter  for Columns100%
Reinforcement & Shutter for RC Walls100%
Pouring of Concrete for Columns100%
Pouring of Concrete for RC Walls100%
Third Floor PT Slab & Beam Shuttering100%
Third Floor PT Slab & Beam Reinforcement100%
Casting of Third Floor PT Slab & Beam100%
 
                       
AREAACTIVITYCOMPLETED
THIRD FLOOR      TO  FOURTH  FLOORReinforcement & Shutter for Columns100%
Reinforcement & Shutter for RC Walls100%
Pouring of Concrete for Columns100%
Pouring of Concrete for RC Walls100%
Fourth Floor PT Slab & Beam Shuttering100%
Fourth Floor PT Slab & Beam Reinforcement100%
Casting of Fourth Floor PT Slab & Beam100%
nnnn

Section 3

nnnn

LIST OF EQUIPMENT

nnnn

III. LIST OF MACHINERY/EQUIPMENT AT SITE

nnnn
  1. 14 Seater bus                  :       1 No.
  2. Generator                               :       2 No.
  3. Hand Cutter                    :       1 No.
  4. Level Machine                :       2 No.
  5. Wood Cutting Machine  :       1 No.
  6.  Water Tank                   :       2 Nos.
  7. Mobile Crane                  :      1 No.
  8. Bending Machine           :       1 No.
  9. Total Station                   :       1 No.
  10. Tower Crane                 :       1 No.
  11. Steel Cutting Machine  :       1 No.
nnnn

Section 4

n

Key Aspects of Monthly Progress Report

nnn

RECORD OF MANPOWER

nnnn

RECORD OF MANPOWER AT SITE FROM SEPTEMBER 1–SEPTEMBER 30 YEAR 2016

nnnn
MonthDateShuttering CarpenterSteel FitterHelperMasonElectricianMachine OperatorRiggerForemanPlumberPainter
September1112253211132
September3172587311134
September4162385411124
September5162576411133
September6132373411134
September7152274311134
September8132275311134
September101820105511134
September1118241410311196
September131217174211164
September141522135411155
September15162555311145
September171415105511155
nnnn
MonthDateShuttering CarpenterSteel FitterHelperMasonElectricianMachine OperatorRiggerForemanPlumberPainter
September18162095311155
September19142395411124
September20162395411122
September21162153411132
September22151774511132
September24171752511132
September25162084411133
September26172264611153
September27111953311143
September28152193511153
September29162274411153
nnnn
 
 
nnnn

Section 5

nnnn

REQUIREMENT OF

nnnn

SUBCONTRACTORS / SUPPLIERS

nnnn

V. Requirement of Subcontractors / Suppliers

nnnn
  1. Plumbing
  2. Electrical
  3. HVAC
  4. Fire fighting
  5. Garbage Chute
  6. Elevator
  7. Sliding Automatic Doors
  8. Landscaping
  9. Sanitary wares and fixtures
  10. Gate Barriers system
  11. Signage
  12. Block work
  13. Plaster
  14. Water proofing wet areas
nnnn
  1. Tiles
  2. Marble / Granite
  3. Interlock
  4. Epoxy
  5. Aluminum Glass & Cladding
  6. Paint
  7. Suspended Ceiling
  8. Metal Works
  9. Roof Water proofing
  10. Door / Joinery / Wood Works / louvers
  11. Glass & Mirrors
  12. Locks and Archive Cabinets
  13. Vanity Counter
  14. Bathroom Partitions
nnnn

Section 6

nnnn

MATERIAL SUBMITTAL LOG

nnnn

Section 7

nnnn

SHOP DRAWING SUBMITTAL LOG

nnnn

Section 8

nnnn

RFI LOG

nnnn

Section 9

nnnn

INSPECTION REQUEST REPORT LOG

nnnn

Section 10

nnnn

METHOD STATEMENT LOG

nnnn

Section 11

nnnn

PROCUREMENT LOG-LONG LEAD ITEMS

nnnn
  1. Procurement Log PC Items
nnnn
PROCUREMENT LOG PC ITEMS
 
nnnn
  1. Granite Tile
  2. Ceramic Tile
  3. Mosaic Tile
  4. Internal Painting
nnnn

5. Precast Wheel Stoppers

nnnn

6. False Ceiling

nnnn

7. Vanity Counter

nnnn

8. Wardrobes

nnnn

Section 11

nnnn

PROCUREMENT LOG-LONG LEAD ITEMS

nnnn

b.   Procurement Log PS Items

nnnn
PROCUREMENT LOG PS ITEMS
 
nnnn
  1. Lift/Elevators and Dumb Waiter
  2. Aluminum and Glazing Works
  3. Joineries and Wooden Works
  4. Swimming Pool Including Finishes Accessories
  5. MEP and Equipment
  6. Façade Signage and Internal Signage
  7. Window Cleaning Equipment
  8. Kitchen / Deep Freezer Equipments / Cabinets
  9. Health Club Equipment’s
nnnn

10. CCTV System and Card Access System

nnnn

11. Supply of Sanitary Fitting and System

nnnn

12. Ironmongries and Electronic Door Lock

nnnn

13. ID Works

nnnn

MEP:

nnnn
  1. Supply of Chillers
  2. Supply of BMS System
  3. Chiller Management System
nnnn

Section 11

nnnn

PROCUREMENT LOG-LONG LEAD ITEMS

nnnn

c.   Procurement Log on Long Lead Items

nnnn
PROCUREMENT LOG ON LONG LEAD ITEMS
nnnn
  1.   Fire Pipe
  2.   Fire Pump
  3.   Interior Design Material
  4.   Manhole
  5.    Drainage Pump
  6.    Fire Fighting System
  7.    Calorifier
  8.    Booster Transfer Pump
  9.    Valves
  10. Auto Control Valve
  11. Fire and Smoke Damper
  12. Variable Air Volume
  13. Control Valves
nnnn
  1. Chilled Water Pump
  2. Pressurization Unit
  3. IV Panel
  4. ATS Panel
  5. Busbar Riser
  6. BMS System
  7. Central Battery
  8. Fan Coil Units
  9. Exhaust and Ventilation Fan
  10. Ahu/fahus
  11. Chiller
  12. Generator
nnnn

Section 12

nnnn

PROGRESS PHOTOS

nnnn

Section 13

nnnn

HSE REPORT

nnnn

VII. HSE REPORT

nnn

Related: Narrative Report for a Baseline Schedule., Window Analysis (time Impact Analysis – Tia) in Construction., Methodology or Technique Use to Determine or Prepare the Extension of Time Claim.

n

 As per the safety plan submitted we are started implementations of safety plan at site  as the following:

nnnn
  1. Site workers/staff Safety Induction are done and Monthly/weekly safety reports/TBT Attached.
  2. Fire extinguishers 12 sets delivered at site and installed at various locations.
nnnn
  • Safety Mandatory and Safety Statistics board has installed at entrance gate and another safety precautions board has installed all over the site.
nnnn
  • Helmets, safety shoes and uniforms are made completion to all staff members and workers at site.
nnnn
  • First aid box has installed at site offices.
nnnn
  • All the safety signage has installed.
nnnn
  • Excavated area has been protected by safety accessories and installed deep excavation board.
n { “@context”: “https://schema.org”, “@type”: “Article”, “headline”: “Monthly Progress Report – MONTHLY PROGRESS REPORT”, “description”: “MONTHLY PROGRESS REPORT reinforced in –situ concrete frame comprising ground floor plus floors, with roof level and services blocks.”, “author”: { “@type”: “Person”, “name”: “Md Abu Zaed Khan” }, “datePublished”: “2021-02-10T19:15:08+04:00”, “dateModified”: “2026-06-17T08:36:04+04:00”, “url”: “https://engineersblog.net/monthly-progress-report/” } { “@context”: “https://schema.org”, “@type”: “BreadcrumbList”, “itemListElement”: [ { “@type”: “ListItem”, “position”: 1, “name”: “Home”, “item”: “https://engineersblog.net/” }, { “@type”: “ListItem”, “position”: 2, “name”: “Reports”, “item”: “https://engineersblog.net/reports/” }, { “@type”: “ListItem”, “position”: 3, “name”: “Monthly Progress Report – MONTHLY PROGRESS REPORT”, “item”: “https://engineersblog.net/monthly-progress-report/” } ] }