MONTHLY PROGRESS REPORT NO. 13
MONTHLY PROGRESS REPORT
nAbout Monthly Progress Report
nnnMonth Ending 30th of September 2016
nnnnProject No : xxx
nnnnProject Title : 2B+GF+14 Floors+ Lower Roof Hotel Building
nnnnClient : xxx
nnnnConsultant : xxxx Consulting Architechs & Engineers
nnnnContractor : xxx Contracting L.L.C.
nnnnTable of Contents:
nnnnExecutive Summary…………………………………………………………………Section 1
nnnnProgress Report………………………………………………………………………Section 2
nnnnList of Equipment…………………………………………………………………. ..Section 3
nnnnRecord of Manpower…………………………………………………………………Section 4
nnnnRequirement of Subcontractors / Suppliers …………………………………………Section 5
nnnnMaterial Submittal Log………………………………………………………………Section 6
nnnnShop Drawing Submittal Log………………………………………………………. Section 7
nnnnRFI Log………………………………………………………………………………Section 8
nnnnInspection Request Report Log………………………………………………….….Section 9
nnnnMethod Statement Log………….…………………………………………………..Section 10
nnnnProcurement Log-Long Lead Items………………………………………………… Section 11
nnnn- Procurement Log PC Items
- Procurement Log PS Items
- Procurement Log on Long Lead Item
Progress Photos……………………………………………………………………. Section 12
nnnnHSE Report………………………………………………………………………… Section 13
nnnnSection 1
nnnnEXECUTIVE SUMMARY
nnnn- Executive Summary
Project Name : 2B + GF + 14 Floors + Lower Roof Hotel Building
nnnnProject Location : Plot No. xxx Al Barsha Dubai, UAE
nnnnClient : xxx
nnnnLead Consultant : xxx Consulting Architects & Engineers
nnnnProject Value : AED: 33,000,000.00
nnnnCommencement Date : 09th September 2015
nnnnProject Finish : 08th January 2017
nnnnProject Duration : 488 days including mobilization
nnnnBuilt up Area : 1,025 m²
nnnnProject Information:
nnnnThe scope of works for the 2B + GF + 14 Floors + Lower Roof Hotel Building consist of the following site works;
nnnn- Substructure foundation, reinforced in –situ concrete frame comprising ground floor plus floors, with roof level and services blocks.
- Internal and external finishes inclusive of waterproofing, insulation, supply and installation of doors and windows and all equipment and facilities identified in the Contract documents.
- The installation of Electro Mechanical Works inclusive of testing and commissioning
- External Works finishing as per specification & Drawings
Overall Progress
nnnnMobilization : 100%
nnnnContract duration : 488 days
nnnnTime elapsed : 386 days – 79.09%
nnnnTime left : 102 days – 20.99 %
nnnnLocation of plot : Plot No. 373-1297 Al Barsha Dubai
nnnnPlot Area : 1025 m²
nnnnTotal GFA : 550 m²
nnnnSection 2
nnnnPROGRESS REPORT
nnnnPROGRESS REPORT
nnnn| AREA | ACTIVITY | COMPLETED |
| GROUND FLOOR TO FIRST FLOOR | Reinforcement & Shutter for Columns | 100% |
| Reinforcement & Shutter for RC Walls | 100% | |
| Reinforcement & Shutter for Retaining Walls | 100% | |
| Pouring of Concrete for Columns | 100% | |
| Pouring of Concrete for Retaining Wall | 100% | |
| Pouring of Concrete for RC Walls | 100% | |
| First Floor PT Slab & Beam Shuttering | 100% | |
| First Floor PT Slab & Beam Reinforcement | 100% | |
| Casting of First Floor PT Slab & Beam | 100% |
| AREA | ACTIVITY | COMPLETED |
| FIRST FLOOR TO SECOND FLOOR | Reinforcement & Shutter for Columns | 100% |
| Reinforcement & Shutter for RC Walls | 100% | |
| Reinforcement & Shutter for Retaining Walls | 100% | |
| Pouring of Concrete for Columns | 100% | |
| Pouring of Concrete for Retaining Wall | 100% | |
| Pouring of Concrete for RC Walls | 100% | |
| Second Floor PT Slab & Beam Shuttering | 95% | |
| Second Floor PT Slab & Beam Reinforcement | 95% | |
| Casting of Second Floor PT Slab & Beam | 100% |
| AREA | ACTIVITY | COMPLETED |
| SECOND FLOOR TO THIRD FLOOR | Reinforcement & Shutter for Columns | 100% |
| Reinforcement & Shutter for RC Walls | 100% | |
| Pouring of Concrete for Columns | 100% | |
| Pouring of Concrete for RC Walls | 100% | |
| Third Floor PT Slab & Beam Shuttering | 100% | |
| Third Floor PT Slab & Beam Reinforcement | 100% | |
| Casting of Third Floor PT Slab & Beam | 100% | |
| AREA | ACTIVITY | COMPLETED |
| THIRD FLOOR TO FOURTH FLOOR | Reinforcement & Shutter for Columns | 100% |
| Reinforcement & Shutter for RC Walls | 100% | |
| Pouring of Concrete for Columns | 100% | |
| Pouring of Concrete for RC Walls | 100% | |
| Fourth Floor PT Slab & Beam Shuttering | 100% | |
| Fourth Floor PT Slab & Beam Reinforcement | 100% | |
| Casting of Fourth Floor PT Slab & Beam | 100% |
Section 3
nnnnLIST OF EQUIPMENT
III. LIST OF MACHINERY/EQUIPMENT AT SITE
- 14 Seater bus : 1 No.
- Generator : 2 No.
- Hand Cutter : 1 No.
- Level Machine : 2 No.
- Wood Cutting Machine : 1 No.
- Water Tank : 2 Nos.
- Mobile Crane : 1 No.
- Bending Machine : 1 No.
- Total Station : 1 No.
- Tower Crane : 1 No.
- Steel Cutting Machine : 1 No.
Section 4
nKey Aspects of Monthly Progress Report
nnnRECORD OF MANPOWER
nnnnRECORD OF MANPOWER AT SITE FROM SEPTEMBER 1–SEPTEMBER 30 YEAR 2016
nnnn| Month | Date | Shuttering Carpenter | Steel Fitter | Helper | Mason | Electrician | Machine Operator | Rigger | Foreman | Plumber | Painter | |
| September | 1 | 11 | 22 | 5 | 3 | 2 | 1 | 1 | 1 | 3 | 2 | |
| September | 3 | 17 | 25 | 8 | 7 | 3 | 1 | 1 | 1 | 3 | 4 | |
| September | 4 | 16 | 23 | 8 | 5 | 4 | 1 | 1 | 1 | 2 | 4 | |
| September | 5 | 16 | 25 | 7 | 6 | 4 | 1 | 1 | 1 | 3 | 3 | |
| September | 6 | 13 | 23 | 7 | 3 | 4 | 1 | 1 | 1 | 3 | 4 | |
| September | 7 | 15 | 22 | 7 | 4 | 3 | 1 | 1 | 1 | 3 | 4 | |
| September | 8 | 13 | 22 | 7 | 5 | 3 | 1 | 1 | 1 | 3 | 4 | |
| September | 10 | 18 | 20 | 10 | 5 | 5 | 1 | 1 | 1 | 3 | 4 | |
| September | 11 | 18 | 24 | 14 | 10 | 3 | 1 | 1 | 1 | 9 | 6 | |
| September | 13 | 12 | 17 | 17 | 4 | 2 | 1 | 1 | 1 | 6 | 4 | |
| September | 14 | 15 | 22 | 13 | 5 | 4 | 1 | 1 | 1 | 5 | 5 | |
| September | 15 | 16 | 25 | 5 | 5 | 3 | 1 | 1 | 1 | 4 | 5 | |
| September | 17 | 14 | 15 | 10 | 5 | 5 | 1 | 1 | 1 | 5 | 5 |
| Month | Date | Shuttering Carpenter | Steel Fitter | Helper | Mason | Electrician | Machine Operator | Rigger | Foreman | Plumber | Painter | |
| September | 18 | 16 | 20 | 9 | 5 | 3 | 1 | 1 | 1 | 5 | 5 | |
| September | 19 | 14 | 23 | 9 | 5 | 4 | 1 | 1 | 1 | 2 | 4 | |
| September | 20 | 16 | 23 | 9 | 5 | 4 | 1 | 1 | 1 | 2 | 2 | |
| September | 21 | 16 | 21 | 5 | 3 | 4 | 1 | 1 | 1 | 3 | 2 | |
| September | 22 | 15 | 17 | 7 | 4 | 5 | 1 | 1 | 1 | 3 | 2 | |
| September | 24 | 17 | 17 | 5 | 2 | 5 | 1 | 1 | 1 | 3 | 2 | |
| September | 25 | 16 | 20 | 8 | 4 | 4 | 1 | 1 | 1 | 3 | 3 | |
| September | 26 | 17 | 22 | 6 | 4 | 6 | 1 | 1 | 1 | 5 | 3 | |
| September | 27 | 11 | 19 | 5 | 3 | 3 | 1 | 1 | 1 | 4 | 3 | |
| September | 28 | 15 | 21 | 9 | 3 | 5 | 1 | 1 | 1 | 5 | 3 | |
| September | 29 | 16 | 22 | 7 | 4 | 4 | 1 | 1 | 1 | 5 | 3 |
Section 5
nnnnREQUIREMENT OF
nnnnSUBCONTRACTORS / SUPPLIERS
nnnnV. Requirement of Subcontractors / Suppliers
nnnn- Plumbing
- Electrical
- HVAC
- Fire fighting
- Garbage Chute
- Elevator
- Sliding Automatic Doors
- Landscaping
- Sanitary wares and fixtures
- Gate Barriers system
- Signage
- Block work
- Plaster
- Water proofing wet areas
- Tiles
- Marble / Granite
- Interlock
- Epoxy
- Aluminum Glass & Cladding
- Paint
- Suspended Ceiling
- Metal Works
- Roof Water proofing
- Door / Joinery / Wood Works / louvers
- Glass & Mirrors
- Locks and Archive Cabinets
- Vanity Counter
- Bathroom Partitions
Section 6
nnnnMATERIAL SUBMITTAL LOG
nnnnSection 7
nnnnSHOP DRAWING SUBMITTAL LOG
nnnnSection 8
nnnnRFI LOG
nnnnSection 9
nnnnINSPECTION REQUEST REPORT LOG
nnnnSection 10
nnnnMETHOD STATEMENT LOG
nnnnSection 11
nnnnPROCUREMENT LOG-LONG LEAD ITEMS
nnnn- Procurement Log PC Items
| PROCUREMENT LOG PC ITEMS | |
- Granite Tile
- Ceramic Tile
- Mosaic Tile
- Internal Painting
5. Precast Wheel Stoppers
nnnn6. False Ceiling
nnnn7. Vanity Counter
nnnn8. Wardrobes
nnnnSection 11
nnnnPROCUREMENT LOG-LONG LEAD ITEMS
nnnnb. Procurement Log PS Items
nnnn| PROCUREMENT LOG PS ITEMS | |
- Lift/Elevators and Dumb Waiter
- Aluminum and Glazing Works
- Joineries and Wooden Works
- Swimming Pool Including Finishes Accessories
- MEP and Equipment
- Façade Signage and Internal Signage
- Window Cleaning Equipment
- Kitchen / Deep Freezer Equipments / Cabinets
- Health Club Equipment’s
10. CCTV System and Card Access System
nnnn11. Supply of Sanitary Fitting and System
nnnn12. Ironmongries and Electronic Door Lock
nnnn13. ID Works
nnnnMEP:
nnnn- Supply of Chillers
- Supply of BMS System
- Chiller Management System
Section 11
nnnnPROCUREMENT LOG-LONG LEAD ITEMS
nnnnc. Procurement Log on Long Lead Items
nnnn| PROCUREMENT LOG ON LONG LEAD ITEMS |
- Fire Pipe
- Fire Pump
- Interior Design Material
- Manhole
- Drainage Pump
- Fire Fighting System
- Calorifier
- Booster Transfer Pump
- Valves
- Auto Control Valve
- Fire and Smoke Damper
- Variable Air Volume
- Control Valves
- Chilled Water Pump
- Pressurization Unit
- IV Panel
- ATS Panel
- Busbar Riser
- BMS System
- Central Battery
- Fan Coil Units
- Exhaust and Ventilation Fan
- Ahu/fahus
- Chiller
- Generator
Section 12
nnnnPROGRESS PHOTOS
nnnnSection 13
nnnnHSE REPORT
nnnnVII. HSE REPORT
nnnRelated: Narrative Report for a Baseline Schedule., Window Analysis (time Impact Analysis – Tia) in Construction., Methodology or Technique Use to Determine or Prepare the Extension of Time Claim.
nAs per the safety plan submitted we are started implementations of safety plan at site as the following:
nnnn- Site workers/staff Safety Induction are done and Monthly/weekly safety reports/TBT Attached.
- Fire extinguishers 12 sets delivered at site and installed at various locations.
- Safety Mandatory and Safety Statistics board has installed at entrance gate and another safety precautions board has installed all over the site.
- Helmets, safety shoes and uniforms are made completion to all staff members and workers at site.
- First aid box has installed at site offices.
- All the safety signage has installed.
- Excavated area has been protected by safety accessories and installed deep excavation board.