1.0 Scope
- This method statement details the method of installation of Generator and ATS according to the Specification Section 16402.
Note : A separate Method Statement Ref. : ETA/MS/E-039 shall be submitted for Testing & Commissioning of Generator and ATS.
2.0 Material
- All materials shall be as per approved material submittals, shop drawing and single line diagram.
- Generator & ATS.
- Cable glands and lugs.
- Identification labels and tags.
3.0 Applicable Location
- Generator: East & West Podium – Ground floor.
- ATS: Tower E1, E2, E3 & W1, W2, W3 – LV Rooms.
4.0 Method
- Storage
- Generator & ATS shall be inspected upon receipt at site for damages and compliance with the approved schematic.
- Upon completion of receiving inspection, the Generator & ATS shall be positioned at the correct locations with suitable crane arrangements.
- Generator & ATS found with transportation damages shall be recorded and notified to the concern party for further action.
- Generator & ATS shall be covered with polythene sheets to protect from dust and moisture.
- Installation
- Generator:
4.2.1.1 Installation Procedure:
- Specification sheets will be checked for the dimension & weight of the generator sets and mounting points.
- DG set of both ratings will be mounted on a concrete plinth.
- Installation locations will be as per approved shop drawings.
- Engine Exhaust System:
- Flexible exhaust tubing will be connected to the engine to take up thermal expansion and generator set movement and vibration.
- Exhaust silencer shall be mounted so that the engine does not support the weight of the silencer.
- Flexible tubing will not be used to form bends or to compensate for misalignment of piping.
- Mufflers and piping will be supported by Non-combustible hangers or supports.
- Precaution shall be taken to rule out any possibility of combustible material coming in contact, close to the exhaust piping. Approved non-combustible material shall be used where exhaust piping pases through combustible walls or ceiling etc.
- Horizontal runs of exhaust piping will be sloped downwards away from the engine to out of doors to avoid condensate water entering engine.
- Installation will be as per approved shop drawings.
- Exhaust pipe opening outside the building shall be arranged to avoid entry of rainwater and shall be fitted with bird guard.
- On confirmation of the routing of the exhaust pipe, the number of bends & length will be communicated to the manufacturers & suitable diameter of exhaust pipe will be selected for minimum back pressure.
- Air Intake and Radiator Exhaust
- Intake and exhaust air louvers will be sized and located to provide sufficient intake air for engine combustion and to provide required airflow through the radiator.
- Duct work with flexible connecting section will be sized and located to provide sufficient intake air for engine combustion and to provide required airflow through the radiator.
- The allowable pressure drop will be checked with the manufacturer after confirming the layout and will informed to the louver supplier / manufacturer, for co-ordination purposes.
- Access for Installation
- Access opening for installing the Generator will be indicated on shop drawings.
4.2.2 ATS :
- Ensure approved documents like shop drawing, electrical room layout are available with the installation team.
- Check the label/marking to ensure that it is the right panel and check the position according to the shop drawing.
- Terminate the incoming and outgoing cable as per single line diagram using proper tools.
- Megger the panels after connecting the compartments.
- Megger the cables before terminating.
- Megger the panel after termination.
- Clean the termination and ATS panel with vacuum cleaner and hand brush to clean the dust and small metal pieces fallen during cable cutting and terminating process.
- Provide identification for all the cable termination as per specification requirement.
- Dress the cables neatly with cable ties / cable cleat.
- Double check the connections by tightening the terminations.
- Inspection shall be offered for QC Verification.
5.0 Records
- QC Inspection Check List.
- Inspection request duly signed-off by NMX and Consultant.
- Attachment
6.1 Inspection Check List for Generator & ATS.