ID drawing, their requirement of back up plywood and request  to review

dry wall partition works

dry wall partition works

Date:xxx

Ref No. xxx

To                    : M/s Gypsemna

Kind Attn          :Ms.Abeer

Project             :2B + G + 14+ Lower Roof Hotels Building on Plot No. xxx at Barsha,  Dubai

Sub:             Regarding ID drawing , their requirement of back up plywood and request  to review

Dear Sir,

With reference to the above, we received the shop drawing from M/ s xxx center, kindly review the supporting system which required in the partition by interior subcontractor as mentioned below:

  1. Kindly review the joinery points and comment for any leakage or flanking transmission, impact and confirmation.

Kindly review and issue your confirmation, So that we can execute the same as requested by client.

Regards,

For xxx Contracting L.L.C

xxx

Project Manager