Contractor’s Letters

Access Control System

Endorsement of LOI and work order by main contractor

Date                : xxx Ref                   : CC/269/AAH/01 To                    : M/S xxx Hospitality Project            : 2B + G + 14+ Lower Roof Hotel Building on Plot No. 373-1297 at Al Barsha 1st, Dubai U.A.E Subject           : Endorsement of LOI and work order by main contractor Dear Sir, With ref. to above, we are main contractor xxx Contracting […]

Endorsement of LOI and work order by main contractor Read Post »

jacketing-of-beam-and-column

Regarding discrepancies in number of bar per column cannot be accommodated and need to redesign

Date:               xxx Ref:                 CC/269/TALA/02 To:                    TALA CONCRETE REPAIRS Kind Attn:       Mr. Abdur Rahman Project:           2B + G + 14+ Lower Roof Hotel Building on Plot No. 373-1297 at Al Barsha  1st, Dubai U.A.E Subject:     Regarding discrepancies in number of bar per column cannot be accommodated and need to redesign Dear Mr. Abdur

Regarding discrepancies in number of bar per column cannot be accommodated and need to redesign Read Post »

jacketing-of-beam-and-column

Regarding query for beam jacketing at site

Date:               xxx Ref:                 CC/269/eF/03 To:                     eFORCE Engineering Consultancies Kind Attn:       Dr. xxx Project:           2B + G + 14+ Lower Roof Hotel Building on Plot No. 373-1297 at Al Barsha   1st, Dubai U.A.E Subject:           Regarding query for beam jacketing at site   Dear Sir, With ref. to above kindly confirm, the 10mm anchor

Regarding query for beam jacketing at site Read Post »

Beam Jacketing

Regarding quotation for strengthening of Beam / Beam jacketing

Date:               xxx Ref:                 CC/269/eF/02 To:                   TALA CONCRETE REPAIRS Kind Attn:     Mr. Abdur Rahman Project:          2B + G + 14+ Lower Roof Hotel Building on Plot No. 373-1297 at Al Barsha  1st, Dubai U.A.E Subject:         Regarding quotation for strengthening of Beam / Beam jacketing Dear Mr. Abdur Rahman, We are attaching the required

Regarding quotation for strengthening of Beam / Beam jacketing Read Post »

Beam Jacketing

Structural Guarantee of the beam jacketing

Date:               xxx Ref:                 CC/269/eF/01 To:                     xxx Engineering Consultancies Kind Attn:       Dr. xxx Project:           2B + G + 14+ Lower Roof Hotel Building on Plot No. 373-1297 at Al Barsha  1st, Dubai U.A.E Subject:           Structural Guarantee of the beam jacketing Dear Sir, With ref. to above, provide us the supervision cost and the

Structural Guarantee of the beam jacketing Read Post »

Materials at site

Request to arrange materials

Date: xxx CC/DG/02/16 To       :              M/s xxx Gulf Project:              2B + G + 14 + Lower Roof Hotels Building, Plot No. 373-1297 at Al Barsha 1st, Dubai Subject:             Request to arrange materials Dear Mr.Jaseem, With ref. to above, we would like to inform that the painting workers are suffering today at site because of

Request to arrange materials Read Post »

Undertaking Letter

Application no xxx- Undertaking letter

Date:xxxRef No: CC/DT/DM/15 To,The Dubai MunicipalityBuilding Control SectionDubai, UAE Project         : 2B+G+14+LR Hotel Building on Plot No. 3731297, Al Barsha, Dubai Sub              : Application no 241570-26-1- Undertaking letter Dear Sir,           “This is in reference to the DM application no 241570-26-1 . We undertake any damage to the existing beams for connections to Steel structure

Application no xxx- Undertaking letter Read Post »

Engineer's Training

Engineers are ready for training required for xxx Contracting L.L.C License no: xxx

Date: xxx Ref no: CC/DT/DM/06/16-1 To The Manager, DM Qualification Section (License) xxx Municipality, Dubai UAE Sub:  Engineers are ready for training required for xxx Contracting L.L.C License no: xxx Dear Sir, With ref. to above and requirement our engineers are ready to take the training immediately with your appointment. So, kindly provide immediate appointment

Engineers are ready for training required for xxx Contracting L.L.C License no: xxx Read Post »

fixing doors

Balance work at 14 th floor and three nos of door not fixed as well as still Architrave not fixed up to now and pool quality work

Date : xxx Ref No. : CC/DESTEC/023 To : M/s. xxx GROUP, PO Box 47395, Sharjah UAE Project : 2B+G+14+Lower Roof Hotels Building on Plot No. 373-1297 at Al Barsha  Subject : Balance work at 14 th floor and three nos of door not fixed as well as  still Architrave not fixed up to now

Balance work at 14 th floor and three nos of door not fixed as well as still Architrave not fixed up to now and pool quality work Read Post »