Contractor’s Letters

awaiting-response

To provide tile supplier name for handicapped toilet, lift lobby including male and female toilet

Date:               xxx Ref:                  xxx Kind Attn         :Mr. xxx Project             :2B + G + 14 + Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai U.A.E. Subject            : To provide tile supplier name for handicapped toilet, lift lobby including male and female toilet Dear Sir, As we received ID drawing for ground […]

To provide tile supplier name for handicapped toilet, lift lobby including male and female toilet Read Post »

Reply - Notice of Delay

Work under hold between 11th to 12th floor vertical element due to over night rain , wind and electrical fault in tower crane

Date:               xxx Ref:                  xxx Kind Attn         :Mr. xxx Project             :2B + G + 14 + Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai U.A.E. Subject            : Intimation for the Work under hold between 11th to 12th floor vertical element due to over night rain , wind and electrical fault in

Work under hold between 11th to 12th floor vertical element due to over night rain , wind and electrical fault in tower crane Read Post »

Letter Sample

Update for the CAR policy- your letter ref no. xxx DT. xxx

Date:               xxx Ref:                  xxx Kind Attn         :Mr. xxx Project             :2B + G + 14 + Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai U.A.E. Subject            : Update for the CAR policy- your letter ref no.xxx DT.xxx Dear Sir, With reference to your letter ref no:AP/269/CC/241 DT.15.02.17 for the above mentioned

Update for the CAR policy- your letter ref no. xxx DT. xxx Read Post »

Site Meeting

To arrange meeting with PT designer from PT subcontractor

Date:               xxx Ref:                  xxx Kind Attn         :Mr. xxx Project             :2B + G + 14 + Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai U.A.E. Subject            : To arrange meeting with PT designer from PT subcontractor Dear Sir, With reference to above , we would like to inform you that, the

To arrange meeting with PT designer from PT subcontractor Read Post »

Engineering Submittals

Intimation of variation at toilet ceiling due to ID drawing issued

Date:               xxx Ref:                  xxx Kind Attn         :Mr. xxx Project             :2B + G + 14 + Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai U.A.E. Subject           : Intimation of variation at toilet ceiling due to ID drawing issued Dear Sir, With reference to above, we would like to inform you that

Intimation of variation at toilet ceiling due to ID drawing issued Read Post »

Reply - Notice of Delay

Comments on review for claim of material at site, invoice no. xx dated   xxx

Date:               xxx Ref:                  xxx Kind Attn         :Mr. xxx Project             :2B + G + 14 + Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai U.A.E. Subject           : Regarding your comments on review for claim of material at site, invoice no. xx dated   xxx Dear Sir, With reference to above, you commented

Comments on review for claim of material at site, invoice no. xx dated   xxx Read Post »

Engineering Submittals

Intimation for the partition wall variation for time and cost

Date:               xxx Ref:                  xxx Kind Attn         :Mr. xxx Project             :2B + G + 14 + Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai U.A.E. Subject           : Regarding intimation for the partition wall variation for time and cost Dear Sir, With reference to above and as per your letter ref no:AP/269/CC/224

Intimation for the partition wall variation for time and cost Read Post »

awaiting-response

Regarding withdrawal of monthly report of Jan xx

Date:               xxx Ref:                  xxx Kind Attn         :Mr. xxx Project             :2B + G + 14 + Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai U.A.E. Subject           : Regarding withdrawal of monthly report of Jan xxx Dear Sir, With reference to above, as per the instruction given by the client during the

Regarding withdrawal of monthly report of Jan xx Read Post »

Site Meeting

Minutes of meeting no.xx

Date:               xxx Ref:                  xxx Kind Attn         :Mr. xxx Project             :2B + G + 14 + Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai U.A.E. Subject           : Regarding Minutes of meeting no.69,  update for MEP , our concern  for other items and mock up room program Dear Sir, With reference to

Minutes of meeting no.xx Read Post »

Vanity Counter

Vanity counter issue and verbal discussion in meeting dated xxx

Date:               xxx Ref:                  xxx Kind Attn         :Mr. xxx Project             :2B + G + 14 + Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai U.A.E. Subject           : Regarding vanity counter issue and verbal discussion in meeting dated 06.02.17 Dear Sir, With reference to above, as we had the meeting with the

Vanity counter issue and verbal discussion in meeting dated xxx Read Post »