Regarding Submission of tile received at site, sent from site and required quantity yet to receive status

Wall Cladding

Date: xxx Ref: CC/269/CM/69 To                          : M/s. xxx, Dubai, UAE Kind Attn              : Ms. xxx Project            : 2B + G + 14+ Lower Roof Hotel Building on Plot No. 373-1297 at Al        Barsha 1st, Dubai U.A.E. Subject     : Regarding Submission of tile received at site, sent from site and required quantity yet to receive status      Dear… Continue reading Regarding Submission of tile received at site, sent from site and required quantity yet to receive status

Tile Status and balance tile requirement by in cooperating the additional realistic wastage in toilet floor and wall.

Broken Tiles

Date: xxx Ref: CC/269/CM/68 To                          : M/s. xxx, Dubai, UAE Kind Attn              : Ms. xxx Project            : 2B + G + 14+ Lower Roof Hotel Building on Plot No. 373-1297 at Al        Barsha 1st, Dubai U.A.E. Subject                 :  Tile Status and balance tile requirement by in cooperating the additional realistic wastage in toilet floor and wall.… Continue reading Tile Status and balance tile requirement by in cooperating the additional realistic wastage in toilet floor and wall.

Regarding Submission of subcontractor xxx CONTROLS & SOLUTION LLC invoice for 10% advance payments and Annexure 01 and 02

Terms and Conditions for Sub contractor for Building Management.

Date                   : xxx Ref                      : CC/269/CM/67 To                       : M/s. xxx, Dubai, UAE Kind Attn           : Mr. xxx Project          : 2B + G + 14+ Lower Roof Hotel Building on Plot No. 373-1297 at Al    Barsha 1st, Dubai U.A.E. Subject              : Regarding Submission of subcontractor ASPIRE CONTROLS & SOLUTION LLC invoice for 10% advance payments… Continue reading Regarding Submission of subcontractor xxx CONTROLS & SOLUTION LLC invoice for 10% advance payments and Annexure 01 and 02

Regarding nomination under heading “by client” and our concern.

subcontractor contract agreement.

Date: xxx Ref: CC/269/CM/67 To                          : M/s. xxx, Dubai, UAE Kind Attn              : Mr. xxx Project            : 2B + G + 14+ Lower Roof Hotel Building on Plot No. 373-1297 at Al        Barsha 1st, Dubai U.A.E. Subject                 : Regarding nomination under heading “by client” and our concern. Dear Sir, With reference to the above subject, we… Continue reading Regarding nomination under heading “by client” and our concern.

Regarding submission of Tile received and balance to received status

Wall Cladding

Date: xxx Ref: CC/269/CM/67 To                          : M/s. xxx, Dubai, UAE Kind Attn              : Mr. xxx Project            : 2B + G + 14+ Lower Roof Hotel Building on Plot No. 373-1297 at Al        Barsha 1st, Dubai U.A.E. Subject                 : Regarding submission of Tile received and balance to received status Dear Sir, With reference to the above subject,… Continue reading Regarding submission of Tile received and balance to received status

Regarding submission of original DO for bathtub and sanitary materials for basement-1 male and female toilet

sanitary-ware

Date: xxx Ref: CC/269/CM/66 To                          : M/s. xxx, Dubai, UAE Kind Attn              : Mr. xxx Project            : 2B + G + 14+ Lower Roof Hotel Building on Plot No. 373-1297 at Al        Barsha 1st, Dubai U.A.E. Subject                 : Regarding submission of original DO for bathtub and sanitary materials for basement-1 male and female toilet Dear Sir,… Continue reading Regarding submission of original DO for bathtub and sanitary materials for basement-1 male and female toilet

Regarding your mail communication xxx at 6.40 PM for the payment for invoice-14 to Chirag Contracting LLC.

Delayed of Salary

Date: xxx Ref: CC/269/CM/64 To                       : M/s. xxx, Dubai, UAE Kind Attn          : Ms. xxx Project         : 2B + G + 14+ Lower Roof Hotel Building on Plot No. 373-1297 at Al        Barsha 1st, Dubai U.A.E. Subject                :Regarding your mail communication 23/07/2017 at 6.40 PM for the payment for invoice-14 to Chirag Contracting LLC. Dear Sir,                                   … Continue reading Regarding your mail communication xxx at 6.40 PM for the payment for invoice-14 to Chirag Contracting LLC.

Regarding mutual consensus for payment to supplier or sub-contractor.

delivery of Tiles and cheque copy.

Date: xxx Ref: CC/269/CM/63 To                       : M/s. xxx, Dubai, UAE Kind Attn          : Mr. xxx Project         : 2B + G + 14+ Lower Roof Hotel Building on Plot No. 373-1297 at Al        Barsha 1st, Dubai U.A.E. Subject                :Regarding mutual consensus for payment to supplier or sub-contractor. Dear Sir,                           With reference above, we would like to inform… Continue reading Regarding mutual consensus for payment to supplier or sub-contractor.

Our earlier letter ref no: CC/269/CM/52 dated: xxx & our concern.

Statement

Date: xxx Ref: CC/269/CM/62 To                       : M/s. xxx, Dubai, UAE Kind Attn          : Mr. xxx Project         : 2B + G + 14+ Lower Roof Hotel Building on Plot No. 373-1297 at Al        Barsha 1st, Dubai U.A.E.      Subject              :Regarding our previous letter ref no: CC/269/CM/52 dated: 04-07-2017 & our concern. Dear Sir,                           With reference to above,… Continue reading Our earlier letter ref no: CC/269/CM/52 dated: xxx & our concern.

Regarding authorization to pay subcontractor/supplier from certified invoice

Contract Documents

Date: xxx Ref: CC/269/CM/61 To                          : M/s. xxx, Dubai, UAE Kind Attn              : Mr. xxx Project            : 2B + G + 14+ Lower Roof Hotel Building on Plot No. 373-1297 at Al        Barsha 1st, Dubai U.A.E. Subject                 : Regarding authorization to pay subcontractor/supplier from certified invoice Dear Sir, With reference to the above, we are hereby… Continue reading Regarding authorization to pay subcontractor/supplier from certified invoice