Date: xxx Ref. xxx Kind Attn: Mr. xxx Project: 2B + G + 14+ Lower Roof Hotels Building Plot No.: xxx at Al Barsha 1st, Dubai Subject: Fixing of Water Faucet & Water Cooler Dear MEP Team, With reference to the above, the water faucet in the wash room is broken and… Continue reading Fixing of Water Faucet & Water Cooler
Author: Md Abu Zaed Khan
Hello, this is Engr. Zaed Khan Planning Engineer, Associate member of Society of Engineers UAE. Expert in construction project planning, FIDIC red book, computation of extension of time claim, Contract agreement and contractual letters.
Site Instruction for MEP works
Date: xxx Ref. xxx Kind Attn: Mr. xxx Project: 2B + G + 14+ Lower Roof Hotels Building Plot No.: xxx at Al Barsha 1st, Dubai Subject: Site Instruction Dear Mr. Tahir, With reference to above mentioned subject, we are hereby conforming that from the next slab we need the following from you.… Continue reading Site Instruction for MEP works
Toilet sequence or drainage Piping
Date: xxx Ref. xxx Kind Attn: Mr. xxx Project: 2B + G + 14+ Lower Roof Hotels Building Plot No.: xxx at Al Barsha 1st, Dubai Subject: Toilet sequence or drainage Piping Dear Mr. Tahir, With reference to above mentioned subject, as we discuss since many months to provide roof coordinated layout with… Continue reading Toilet sequence or drainage Piping
Regarding no worker from our end to complete the remaining works and hand over the site
Date: xxx Ref. xxx To: M/s. xxx , Metal Wowks Project: 2B + G + 14 + Lower Roof Hotels Building on Plot No. xxx at Barsha, Dubai Subject : Regarding no worker from our end to complete the remaining works and hand over the site Dear Engr. Mansour , With reference… Continue reading Regarding no worker from our end to complete the remaining works and hand over the site
Regarding cost variation for modification and main entrance area Glazing work around the revolving door at G.F
Date: xxx Ref. xxx To: M/s. xxx , Metal Wowks Project: 2B + G + 14 + Lower Roof Hotels Building on Plot No. xxx at Barsha, Dubai Subject : Regarding cost variation for modification and main entrance area Glazing work around the revolving door at G.F Dear Engr. Mansour , With reference… Continue reading Regarding cost variation for modification and main entrance area Glazing work around the revolving door at G.F
Regarding Pending Works and Holding Our Works
Date: xxx Ref. xxx To: M/s. xxx , Metal Wowks Project: 2B + G + 14 + Lower Roof Hotels Building on Plot No. xxx at Barsha, Dubai Subject : Regarding Pending Works and Holding Our Works Dear Engr. Mansour , With reference to the above mentioned subject, we would like to invite… Continue reading Regarding Pending Works and Holding Our Works
Regarding Demobilize your Office as well as your program to complete the 100% work in writing
Ref. xxx To: M/s. xxx , Metal Wowks Project: 2B + G + 14 + Lower Roof Hotels Building on Plot No. xxx at Barsha, Dubai Subject : Regarding Demobilize your Office as well as your program to complete the 100% work in writing as well as replacement of temporary glasses from front… Continue reading Regarding Demobilize your Office as well as your program to complete the 100% work in writing
Regarding to complete balance work, DCD inspection and issue
of cradle rent to complete balance work Date: xxx Ref. xxx To: M/s. xxx , Metal Wowks Project: 2B + G + 14 + Lower Roof Hotels Building on Plot No. xxx at Barsha, Dubai Subject : Regarding to complete balance work, DCD inspection and issue of cradle rent to complete balance… Continue reading Regarding to complete balance work, DCD inspection and issue
complete the balance work at front elevation, at main entrance around the revolving door
Date: xxx Ref. xxx To: M/s. xxx , Metal Wowks Project: 2B + G + 14 + Lower Roof Hotels Building on Plot No. xxx at Barsha, Dubai Subject : Regarding to complete the balance work at front elevation, at main entrance around the revolving door, ramp side elevation (elevation no.4) and GL… Continue reading complete the balance work at front elevation, at main entrance around the revolving door
Confirmation to fix window frame as per available site opening for GL-22, 12 No’s, Elevation No: 4
Date: xxx Ref. xxx To: M/s. xxx , Metal Wowks Project: 2B + G + 14 + Lower Roof Hotels Building on Plot No. xxx at Barsha, Dubai Subject : Confirmation to fix window frame as per available site opening for GL-22, 12 No’s, Elevation No: 4 Dear Mr. Sajith , With reference… Continue reading Confirmation to fix window frame as per available site opening for GL-22, 12 No’s, Elevation No: 4