False ceiling work

Notification of Claims for Ceiling Suspension System Damaged by xxx

M/s xxx Properties LLC

P.O. Box xxx, Dubai, U.A.E.                                

Tel: xxx

Fax: xxx

Attention        :   Engr. xxx

                            Project Manager                             

Project            :  (G+7F) xxx Apartment – Civil Works

Subject           :  Notification of Claims for Ceiling Suspension System Damaged by
                        ASCON

Dear Sir,

We refer to our Work Order reference xxx dated 23rd June xxx regarding the Fit-Out Works for the Entrances Lobbies and Health Clubs of G-11, G-12 and G-13 where we are currently progressing on site to meet the required completion date, however, we would like to draw your attention regarding the uncoordinated works carried out by the Main Contractor that resulted in damages to our installed ceiling suspension system as shown on the attached photos.

Please be informed that this letter serve as our Notice of Claim for additional time and cost due to the damaged to our ceiling system, all the relevant cost details will be forwarded to you in due course. Moreover, we will start the rectification of the damaged ceiling once the necessary clearance to proceed with our works is issued in order to avoid similar incident like this, any delays due to this is not under Xxx(Name of the Subcontractor) Interiors’ responsibility.

Meanwhile, we request you to instruct all relevant parties working on the project to avoid damaging the works of other parties and to always coordinate in order to avoid such incident.

This is for your information and necessary action.

Sincerely Yours,

For Xxx(Name of the Subcontractor) Interiors LLC                                    

xxx

Project Manager

Leave a Comment

Your email address will not be published. Required fields are marked *

Scroll to Top