Door Frame installation

Damages to Joinery Works

M/s xxx Building Contracting LLC       

PO Box xxx, Dubai, U.A.E

T: xxx | F: xxx

Email: xxx

Attention        :   MR. xxx

    Project Manager

 Project         :   xxx Sky Tower – Umm Ramool

Subject        :   Damages to Joinery Works

Dear Sir,

We would like to draw your attention to the continuous damages being done on the installed joinery works due to the incomplete works by others which will affect the project completion due to the required rectification (refer to the attached details).

In view of this, Xxx (Name of the Subcontractor) Interiors reserve its rights to claim for additional cost and extension of time due to the necessary rectification required, all the relevant details will be submitted in due course.

This is for your information, reference and record.

Sincerely Yours,

For Xxx (Name of the Subcontractor) Interiors LLC

xxx

Commercial Manager