Delay in Mock-up Material Delivery

Delay in Mock-up Material Delivery

M/s xxx Building Contracting LLC       

PO Box xxx, Dubai, U.A.E

T: xxx | F: xxx

Email: xxx

Attention        :   MR. xxx

    Project Manager

 Project         :   xxx Sky Tower – Umm Ramool

Subject:            Delay in Mock-up Material Delivery

Dear Sir,

We acknowledge receipt of your letter reference xxx dated 5th September xxx regarding the alleged delay in mock-up flat material delivery and would like to assure you that we are doing our utmost best to comply with the requirements in providing the materials for the mock-up flat.

Please be informed that yesterday, 5th September xxx we have delivered the doors for the mock-up flat (refer to the attached delivery note) and we are currently manufacturing the Kitchen Cabinets, Vanity and Wardrobes and tentative delivery will be on 10th September xxx.

This is for your information, reference and record.

Sincerely Yours,

For Xxx (Name of the Subcontractor) Interiors LLC

xxx

Commercial Manager