Our Ref: xxx
Date: xxx
To : xxx Engineering & Contracting Co. (L.L.C.)
P. O. Box xxx
Dubai
U.A.E.
Attention : Engg. xxx
Project : xxx Town Houses
Subcontract Agreement Ref No.:xxx
Subject : TYPE “C” – Mock up Pods.
Dear Mr. xxx,
Based on the approved shop drawings received on 2nd of February, we require minimum 15 days to produce the 3 ground floor pods. The mould works for the floors are already stated and these are expected to cast only on Wednesday 11th of February.
The latest delivery of the ground floor pods will be on 18th of February at site. We will do all possible to improve this date and will update you accordingly.
Hope you will understand the situation and cooperate with us.
Yours faithfully,
On behalf of xxx LLC
xxx
Projects Manager