Subject: Check and Priority Lists with Confirmation Date
Dear Sir
With reference to the above mentioned subject and as yesterday meeting discussion. We would like to inform you that you need to send us today the ff:
- Check and Priority List work particular at Roof Area
- Duct reduce size at Lift Lobby Area ( Lower Roof)
- Ground Floor Lift lobby Clearance
With this we come to know what are remaining works and related works need to be prioritized, to us to do the parallel with other activity.
As we all know we only have small remaining time for the handing over of the building.
So, please do the necessary works.
In this regards your cooperation is highly appreciated.
Thanking you