Dry Wall partition Work, request to review under clause

Date:               xxx Ref:                  xxx Kind Attn         :Mr. xxx Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. 373-1297 at Al Barsha 1st, Dubai U.A.E Subject:           Response to your letter ref.AP/269/CC/282 DT.20.03.17-Dry Wall partition Work, request to review under clause 2.6 Dear Sir, With reference to the above, we are not confirming our acceptance for the clarification […]

Delay in the nomination of the vanity counter.

Date:               xxx Ref:                  xxx Kind Attn         :Mr. xxx Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. 373-1297 at Al Barsha 1st, Dubai U.A.E Subject:           Your comment for our submittal CC/AP/269/SH/CIV/ID/012  dated 15.03.17-  shop drawing for 2nd floor unit-5 vanity counters fixing details and delay in the nomination of the vanity counter. Dear Sir, With reference […]

Rework to fix the plywood in mock up room and intimation for variation work

Date:               xxx Ref:                  xxx Kind Attn         :Mr. xxx Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. 373-1297 at Al Barsha 1st, Dubai U.A.E Subject:          Regarding rework to fix the plywood in mock up room and intimation for variation work under clause 53.1 Dear  Sir, With reference to the above, we received the drawing from M/ […]

Release draft contract document for M/s xxx Center

Date:               xxx Ref:                  xxx Kind Attn         :Mr. xxx Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. 373-1297 at Al Barsha 1st, Dubai U.A.E Subject:          Regarding to release draft contract document for M/s xxx Center Dear  Sir, With refernce to the above, we already isused the LPO to M/s xxx center , but you did not […]

Dry wall partition work delay issue and intimation for the rework of partition

Date:               xxx Ref:                  xxx Kind Attn         :Mr. xxx Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. 373-1297 at Al Barsha 1st, Dubai U.A.E Subject:           Regarding dry wall partition work delay issue and intimation for the rework of partition at second floor Dear  Sir, With due respect and subject mentioned for delay in your previous communications […]

Tile delivery confirmation at our site from M/s xxx General Trading LLC

Date:               xxx Ref:                  xxx Kind Attn         :Mr. xxx Project             :2B + G + 14 + Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai U.A.E. Subject           : Regarding tile delivery confirmation at our site from M/s Bymet General Trading LLC (Partial  delivery) Dear Sir, With reference to the above, kindly find our confirmation/ inspection  for the […]

Dry wall partition  work –delay and variation

Date:               xxx Ref:                  xxx Kind Attn         :Mr. xxx Project             :2B + G + 14 + Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai U.A.E. Subject        : Response to your letter ref :AP/269/CC/270, DT.11.03.17, regarding dry wall partition  work –delay and variation Dear Sir, With reference to the above, please note that our entire communication mentioned […]

Submission of Documents of Swimming Pool –Environmental Dept. Approval

Date:               xxx Ref:                  xxx Kind Attn         :Mr. xxx Project             :2B + G + 14 + Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai U.A.E. Subject:          Submission of Documents of Swimming Pool –Evironmental Dept.Approval Dear  Sir, With reference to above subject, we are hereby submitting the following documents as per your letter ref no.AP/269/CC/243 DT.15.02.17 & […]

Revise submission for partition as per your instruction

Date:               xxx Ref:                  xxx Kind Attn         :Mr. xxx Project             :2B + G + 14 + Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai U.A.E. Subject           : Regarding revise submission for partition as per your instruction ref no: AP/269/CC/270, DT.11.03.17, mentioned in item no.01 on page 02 of 02 Dear Sir, With reference to the above, […]

Addition of admixture in Approved Mix Design

Date:               xxx Ref:                  xxx Kind Attn         :Mr. xxx Project             :2B + G + 14 + Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai U.A.E. Subject:          Addition of admixture in Approved Mix Design to Overcome Friction Losses and Maintain Design Slump at  Slab Pouring Level Dear  Sir,       With reference to above subject, as  we experience […]