Undertaking Letter

Application no xxx- Undertaking letter

Date:xxxRef No: CC/DT/DM/15 To,The Dubai MunicipalityBuilding Control SectionDubai, UAE Project         : 2B+G+14+LR Hotel Building on Plot No. 3731297, Al Barsha, Dubai Sub              : Application no 241570-26-1- Undertaking letter Dear Sir,           “This is in reference to the DM application no 241570-26-1 . We undertake any damage to the existing beams for connections to Steel structure […]

Application no xxx- Undertaking letter Read Post »

construction joint for the pool

Undertaking for the construction joint for the pool construction at LB-102 for pool slab and method statement.

Date: xxx Ref no: CC/DT/DM/14 To, Dubai Municipality Building Control section Dubai, UAE Project      : 2B + G + 14+ Lower Roof Hotels Building on Plot No. 373-1297 at Barsha, Dubai Sub             : Undertaking for the construction joint for the pool construction at LB-102 for pool slab and method statement. Dear Sir, With reference to

Undertaking for the construction joint for the pool construction at LB-102 for pool slab and method statement. Read Post »

Concreting-of-reinforced-concrete-slab-photo-by-the-author-of-the-paper

Undertaking for law height form work for slab above ettic slab (0.7m height) and pool deck.

Date: xxx Ref no: CC/DT/DM/13 To, Dubai Municipality Building Control section Dubai, UAE Project      : 2B + G + 14+ Lower Roof Hotels Building on Plot No. 373-1297 at Barsha, Dubai Sub               : Undertaking for law height form work for slab above ettic slab (0.7m   height) and pool deck. Dear Sir, With reference to the

Undertaking for law height form work for slab above ettic slab (0.7m height) and pool deck. Read Post »

PT WORKS

Submission of the proposal to close the distribution pump opening in PT slab from 4th floor to roof located in corridor

Date: xxx Ref no: CC/DT/DM/12 To, Dubai Municipality Building Control section Dubai, UAE Project        : 2B + G + 14+ Lower Roof Hotels Building on Plot No. 373-1297 at Barsha, Dubai Sub                : Submission of the proposal to close the distribution pump opening in PT slab from 4th floor to roof located in corridor Dear

Submission of the proposal to close the distribution pump opening in PT slab from 4th floor to roof located in corridor Read Post »

Beam Jacketing

Undertaking letter by Main contractor for structural safety /building safety as required in application no: xxx.

Date: xxx Ref no: CC/DT/DM/09 To, Dubai Municipality Building permit section Dubai, UAE Project       :    2B + G + 14+ Lower Roof Hotels Building on Plot No. 373-xxx at Barsha, Dubai Sub      :  Undertaking letter by Main contractor for structural safety /building    safety as  required in application no:241570-23-1. Dear Sir, With reference to the

Undertaking letter by Main contractor for structural safety /building safety as required in application no: xxx. Read Post »

Engineer's Training

Engineers are ready for training required for xxx Contracting L.L.C License no: xxx

Date: xxx Ref no: CC/DT/DM/06/16-1 To The Manager, DM Qualification Section (License) xxx Municipality, Dubai UAE Sub:  Engineers are ready for training required for xxx Contracting L.L.C License no: xxx Dear Sir, With ref. to above and requirement our engineers are ready to take the training immediately with your appointment. So, kindly provide immediate appointment

Engineers are ready for training required for xxx Contracting L.L.C License no: xxx Read Post »

fixing doors

Balance work at 14 th floor and three nos of door not fixed as well as still Architrave not fixed up to now and pool quality work

Date : xxx Ref No. : CC/DESTEC/023 To : M/s. xxx GROUP, PO Box 47395, Sharjah UAE Project : 2B+G+14+Lower Roof Hotels Building on Plot No. 373-1297 at Al Barsha  Subject : Balance work at 14 th floor and three nos of door not fixed as well as  still Architrave not fixed up to now

Balance work at 14 th floor and three nos of door not fixed as well as still Architrave not fixed up to now and pool quality work Read Post »