To fix the floor tile in first floor corridor outside of All Day Dining

To fix the floor tile in first floor corridor outside of All Day Dining

Date:xxx
Ref No.:CC/DESTEC/021
To:M/s. xxx GROUP, PO Box 47395, Sharjah UAE
Project:2B+G+14+Lower Roof Hotels Building on Plot No. 373-1297 at Al Barsha 
Subject:To fix the floor tile in first floor corridor outside of All Day Dining

Dear Mr.xxx,

With reference to the above, we have issued variation work to fix the tile/ continue from All Day Dining area to consider/passage.

So, up to how you didn’t execute the scope and variation instruction issued to you by client long before.

 Kindly do needful as soon as possible and acknowledge the same.

Best Regards

For xxx Contracting LLC

xxx

Project Manager