Date: xxx

Ref no: CC/DT/DM/17

To,

Dubai Municipality

Dubai, UAE

Project        : 2B + G + 14+ Lower Roof Hotels Building on Plot No. 373-xxx at Barsha, Dubai

Sub            :   Incident Report and Documents Submission

Dear Sir,

With reference to the above, we are submitting all the required documents as per your instructions and as per your list provided as follows:

1. Building Permit  / Affection Plan and Chirag  Trade License

2. Incident report

3. Equipment Third Party Certificate

4. License of the   Tower Crane operator

5. Approved DM drawing to indicate the location

6. Risk Assestment

So, this is for your kind record and fulfill your requirement

Regards,
For xxx Contracting L.L.C