Pod Delivery Schedule

Pod Delivery Schedule

Our Ref: xxx

Date: xxx

To                    :           xxx Construction Co. L.L.C.

                                    P. O. Box xxx

            Dubai – UAE.

Attention          :           xxx

                        :           Sr. Project Manager

Project             :           xxx Park Hotel Dubai

Subject            :           xxx response against letter pertaining “Abortive works to structural slab for Pod drainage penetration”

Dear Mr. xxx,

We received your letter regarding the abortive works to structural slab for Pod drainage penetration and xxx don’t agree to any sort of cost deduction from our certifications.

Please note that the site already have a lot of discrepancies in coring as we all know and xxx is still supporting this project to a big extent to overcome the delays. We would like to remind you that we had produced around 250 different types of pods against 4 types of pods originally to support the project for which we have all rights to claim for a Variation of Contract.

However Please note the below points for your information and record,

Pod NoTypical/Non-TypicalPod As per approved drawingRemarks
2R-1-3-03Non-TypicalYes – physically verified at site2 MM difference from site coring
6R-1-3-81Non-TypicalYes – physically verified at site2 MM difference from site coring
7R-1-4-15Non-TypicalYes – physically verified at sitexxx – Drawing was wrong
7L-1-4-14Non-TypicalYes – physically verified at site2MM difference from site coring
Type-1RTypicalYes – physically verified at site12-15 mm difference from coring

Accordingly we would expect the same spirit of cooperation from xxx what we showed towards your project so that we can complete this project as a team successfully.

This is for your information and record.

Yours faithfully,