METHOD STATEMENT FOR WIRES AND CABLES INSTALLATION

METHOD STATEMENT FOR WIRES AND CABLES INSTALLATION

Our Ref: xxx

Date: xxx

To                    :           xxx Contracting Middle East,

                                   P.O.Box xxx,

                                   Dubai, UAE 

Attention          :           Ms. xxx

                        :           Project Director

Project             :           xxx Tower Views, Dubai

Subject                 : xxx Cables – A proposal for a solution for your kind consideration

Dear Eng. xxx,

We believe there is lots of misperceptions surrounding the delivery of xxx Cables.  The aim of this message is to clarify what happened and propose two solutions for your kind consideration.

  1. The History
  2. The supplier confirmed that LSF cables will take minimum 10 weeks from order placement and payment date.  If we assume that Xxx placed the order and made the payment by 15th of August xxx, which means within a week and a half from the Subcontract, the cables would reach Xxx in the beginning of November 2019.
  3. The above schedule was not acceptable as it would delay the overall delivery of the pods.  For this reason, Xxx could not place the order and make the payment until a solution is found i.e. or we incentivize the supplier to reduce the delivery period, or an alternative is found.  Please refer to our letter Ref: xxx dated xxx for the full list.

Yours faithfully,

On behalf of xxx LLC