Ref: xxx
Date: xxx
To:
P.O Box: xxx
Tel: xxx, Fax: xxx
Project : 2B+G+7 Residential Building, ICP1 CBD C01, International City
Client : M/s xxx Properties Ltd
Consultant : M/s xxx Engineering Consultant.
Subject: Undertaking letter for temporary scaffold for swimming pool deck slab before concrete.
Dear Sir
Referring to the above, please note that the works for the swimming pool deck slab erected for slab and it is inspected and safe to carry load for concrete as live load, height of is very low and safe.
This certificate is given on the basis of materials erected based on our design drawings submitted approved by your office.
Area (as per drawings): Swimming pool deck.
Height : 1.5 m (floor height)
Slab Thickness : 150 mm thick (solid slab)
For xxx Contracting LLC
xxx
General Manager