Date: xxx
Ref: xxx
Kind Attn :Mr. xxx
Project: 2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai
Subject : Our Undertaking Letter for Inspection and Comment for Rejection for
Access at elevation no2 between grid 2 to 5 and 7 to 9 floor.
Dear Sir,
With reference to the above subject, we are hereby requesting you that because of the Sub-station and Tower Crane we are unable to give the safe access for your inspection at height for external plaster between grid 2 to 5 and between floor 7 to 9.
So, we are hereby undertaking to allow us to work in our risk and cost and to execute for the same as we are in very tight schedule.
Kindly allow us with this undertaking.
Regards,
For xxx Contracting L.L.C.
xxx
Project Manager