Tiling work under hold at Basement toilet

Tile Installation

Date:               xxx

Ref:                  xxx

Kind Attn         :Mr. xxx

Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai

Subject         Regarding tiling work under hold at Basement toilet, Ground floor and First floor

Dear Sir,

With reference to above , we have provided the BOH quantity  through our vide letter ref no: CC/AP/201/16  on dated 05.12.16  and we received the nomination  only for typical floor sanitary ware supplier  (AP/269/290 DT.17.01.17 ) and for  rest of the building  ,till date we have not received any nomination . Kindly note the following:

  1. Without providing the sanitary ware material , we cannot complete the block work and plaster to fix the tile at any basement , ground floor and first floor and it holding our civil work prior to hand over the site to interior team and all area under hold since Nov,2016.

Furthermore, we would like to intimate you that,due to  non avalaibility of sanitary ware, the tiling work from Basement to First floor under hold and Contractor should not be  held responsible for delay of the work and have “rights reserved” to claim the extension of time and cost.

Regards,

For xxx Contracting L.L.C.

xxx

Project Manager